Valero Refinery Corpus Christi West is a 69.2 MW power plant, 57.2 MW of it petroleum, in Nueces County, Texas, operated by Valero Refining Co, and it generated 82,083 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 86th percentile of U.S. petroleum plants. By 2025 generation it ranks 3,617th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

69.2 MWNameplate capacity
7%Capacity factor, 2025, petroleum units, 86th percentile, on 53.2 MW net summer
3,617thU.S. rank by generation, 2025
42 yearsAverage generator age, by MW

How hard does the Valero Refinery Corpus Christi West plant run compared with other petroleum plants?

The Valero Refinery Corpus Christi West plant's petroleum units had a capacity factor of 7% in 2025 on 53.2 MW of net summer capacity, the 86th percentile of the 143 U.S. petroleum plants with at least 20 MW. The typical petroleum plant reached 1%. That equals about 27 days at full output out of 365.

0%Shaded: the middle half of petroleum plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Valero Refinery Corpus Christi West7%
Petroleum plants, 75th percentile1%
Petroleum plants, median1%
Petroleum plants, 25th percentile0%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its petroleum generators only. Values above 105% are left out of the comparison.

Is the Valero Refinery Corpus Christi West plant generating more or less than last year?

Generation at Valero Refinery Corpus Christi West fell 17.3% from 2024 to 2025, from 99,303 MWh to 82,083 MWh. Through August 2026 it is running 3.2% ahead of the same months of 2025.

Net generation by period
PeriodMWh
202499,303
202582,083
2026 through August60,592
2025, same months58,740
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 20265,599
July 20266,881
June 20267,374
May 20269,975
April 20266,276
March 20267,226
February 20268,888
January 20268,373
December 20257,115
November 20254,714
October 20255,662
September 20255,852
August 20258,140
July 202510,432
June 20256,846
May 20258,003
April 20256,608
March 20257,777
February 20255,203
January 20255,731
December 20245,458
November 20246,761
October 20248,724
September 20246,874
August 20246,184
July 20247,440
June 20247,527
May 20248,393
April 20249,446
March 202410,244
February 20249,890
January 202412,362

Source: EIA Form EIA-923, through August 2026.

How much of Texas' electricity comes from the Valero Refinery Corpus Christi West plant?

Valero Refinery Corpus Christi West made 0.0% of the 592,896,176 MWh reported by Texas plants in 2025, from 0.0% of the state's 195,966 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 569th largest of 1,023 plants in Texas, the 3,377th largest of 14,327 in the U.S. and the 86th largest of 861 petroleum plants on its petroleum units alone. By 2025 generation it is the 506th largest of 816 generating plants in the state.

Valero Refinery Corpus Christi West within Texas, 2025
MeasureThis plantTexasShare
Capacity (MW)69195,9660.0%
Generation (MWh)82,083592,896,1760.0%
Petroleum capacity (MW)578496.7%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Valero Refinery Corpus Christi West plant, and when do they retire?

3 operable generators total 69.2 MW, with an average age of 42 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860. 1 has already retired, totalling 7.5 MW.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1980s369100%none reported
Every generator, 4 in all
UnitStatusTechnologyMWIn servicePlanned retirement
PRUOperatingAll Other121983n/a
TG1OperatingPetroleum Coke291983n/a
TG2OperatingPetroleum Coke291983n/a
TG3RetiredOther Gases819862006

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Valero Refinery Corpus Christi West plant?

EIA lists no joint owners for Valero Refinery Corpus Christi West. Valero Refining Co operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What fuels does the Valero Refinery Corpus Christi West plant use?

Valero Refinery Corpus Christi West has capacity on 2 fuels: 83% petroleum and 17% other-fuel. In 2025, petroleum made 42% of its output.

Capacity and 2025 generation by fuel
FuelMWShare2025 MWh
Petroleum5782.7%34,749
Other-fuel1217.3%32,696

Source: EIA Forms EIA-860 and EIA-923, 2025.

Where is the Valero Refinery Corpus Christi West plant?

Valero Refinery Corpus Christi West is in Corpus Christi, Nueces County, Texas, at 27.8175° N, 97.4814° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).

Source: EIA Form EIA-860, Plant, 2025 final.

Which petroleum plants in Texas are similar in size?

Texas has 29 operable petroleum plants with 849 MW of capacity, and Valero Refinery Corpus Christi West's 57.2 MW is 7% of that.

Petroleum plants in Texas around this size
PlantCountyMW2025 MWh
Powerlane PlantHunt68718
Valero Refinery Corpus Christi WestNueces5734,749

Source: EIA Forms EIA-860 and EIA-923, 2025.