Biomass power plant, Georgia
WestRock Southeast, LLC. biomass power plant, Georgia
WestRock Southeast, LLC. is a 82.1 MW power plant, 45 MW of it biomass, in Laurens County, Georgia, operated by WestRock Southeast, LLC, and it generated 187,259 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Georgia, and its capacity factor sits at the 7th percentile of U.S. biomass plants. By 2025 generation it ranks 2,583rd of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the WestRock Southeast, LLC. plant run compared with other biomass plants?
The WestRock Southeast, LLC. plant's biomass units had a capacity factor of 21% in 2025 on 44 MW of net summer capacity, the 7th percentile of the 167 U.S. biomass plants with at least 20 MW. The typical biomass plant reached 48%. That equals about 78 days at full output out of 365.
0%Shaded: the middle half of biomass plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| WestRock Southeast, LLC. | 21% |
| Biomass plants, 75th percentile | 65% |
| Biomass plants, median | 48% |
| Biomass plants, 25th percentile | 35% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its biomass generators only. Values above 105% are left out of the comparison.
Is the WestRock Southeast, LLC. plant generating more or less than last year?
Generation at WestRock Southeast, LLC. rose 1.9% from 2024 to 2025, from 183,781 MWh to 187,259 MWh. Through August 2026 it is running 57.2% behind the same months of 2025.
2 months show net generation below zero, when the plant used more power than it sent out, so the months are listed below rather than charted.
| Period | MWh |
|---|---|
| 2024 | 183,781 |
| 2025 | 187,259 |
| 2026 through August | 53,973 |
| 2025, same months | 126,092 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 16,141 |
| July 2026 | 12,941 |
| June 2026 | 254 |
| May 2026 | -2,019 |
| April 2026 | 17 |
| March 2026 | -873 |
| February 2026 | 11,839 |
| January 2026 | 15,674 |
| December 2025 | 15,713 |
| November 2025 | 15,059 |
| October 2025 | 15,385 |
| September 2025 | 15,010 |
| August 2025 | 15,128 |
| July 2025 | 20,796 |
| June 2025 | 16,166 |
| May 2025 | 14,404 |
| April 2025 | 15,291 |
| March 2025 | 15,495 |
| February 2025 | 13,058 |
| January 2025 | 15,755 |
| December 2024 | 14,244 |
| November 2024 | 10,349 |
| October 2024 | 13,793 |
| September 2024 | 15,862 |
| August 2024 | 19,347 |
| July 2024 | 17,773 |
| June 2024 | 14,842 |
| May 2024 | 15,622 |
| April 2024 | 13,108 |
| March 2024 | 15,782 |
| February 2024 | 13,719 |
| January 2024 | 19,340 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the WestRock Southeast, LLC. plant, and when do they retire?
2 operable generators total 82.1 MW, with an average age of 36 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1980s | 2 | 82 | 100% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GEN1 | Operating | Wood/Wood Waste Biomass | 45 | 1989 | n/a |
| GEN2 | Operating | Natural Gas Fired Combustion Turbine | 37 | 1989 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the WestRock Southeast, LLC. plant?
EIA lists no joint owners for WestRock Southeast, LLC.. WestRock Southeast, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What fuels does the WestRock Southeast, LLC. plant use?
WestRock Southeast, LLC. has capacity on 2 fuels: 55% biomass and 45% natural gas. In 2025, biomass made 44% of its output.
| Fuel | MW | Share | 2025 MWh |
|---|---|---|---|
| Biomass | 45 | 54.8% | 82,100 |
| Natural gas | 37 | 45.2% | 41,189 |
Source: EIA Forms EIA-860 and EIA-923, 2025.
Where is the WestRock Southeast, LLC. plant?
WestRock Southeast, LLC. is in Dublin, Laurens County, Georgia, at 32.5036° N, 82.8443° W. It sits in the Southern Company Services, Inc. - Trans balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which biomass plants in Georgia are similar in size?
Georgia has 23 operable biomass plants with 882 MW of capacity, and WestRock Southeast, LLC.'s 45 MW is 5% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| GRP Madison Renewable Energy Facility | Madison | 58 | 423,403 |
| Albany Green Energy | Dougherty | 55 | 106,085 |
| Clearwater Paper Corporation - Augusta | Richmond | 46 | n/a |
| WestRock Southeast, LLC. | Laurens | 45 | 82,100 |
Source: EIA Forms EIA-860 and EIA-923, 2025.