Wind power plant, Washington

Wild Horse wind power plant, Washington

Wild Horse is a 273 MW wind power plant in Kittitas County, Washington, operated by Puget Sound Energy Inc, and it generated 590,982 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.6% of the generation reported in Washington, and its capacity factor sits at the 22nd percentile of U.S. wind plants. By 2025 generation it ranks 1,142nd of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

273 MWNameplate capacity
25%Capacity factor, 2025, 22nd percentile, on 271 MW net summer
0.6%Of WA generation, 2025
19 yearsAverage generator age, by MW

How hard does the Wild Horse plant run compared with other wind plants?

The Wild Horse plant had a capacity factor of 25% in 2025 on 271 MW of net summer capacity, the 22nd percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 91 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Wild Horse25%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Wild Horse plant generating more or less than last year?

Generation at Wild Horse fell 7.2% from 2024 to 2025, from 636,790 MWh to 590,982 MWh. Through August 2026 it is running 5.8% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024636,790
2025590,982
2026 through August417,411
2025, same months394,559
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202641,361
July 202651,259
June 202668,732
May 202648,070
April 202653,368
March 202681,645
February 202638,004
January 202634,972
December 202559,207
November 202550,310
October 202559,181
September 202527,725
August 202535,317
July 202555,415
June 202560,117
May 202560,315
April 202556,708
March 202562,569
February 202536,629
January 202527,489
December 202440,669
November 202447,204
October 202460,972
September 202447,576
August 202437,768
July 202449,276
June 202467,223
May 202478,749
April 202474,828
March 202448,854
February 202450,863
January 202432,808

Source: EIA Form EIA-923, through August 2026.

How much of Washington's electricity comes from the Wild Horse plant?

Wild Horse made 0.6% of the 101,512,862 MWh reported by Washington plants in 2025, from 0.9% of the state's 31,712 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 25th largest of 139 plants in Washington, the 1,170th largest of 14,327 in the U.S. and the 117th largest of 1,358 wind plants. By 2025 generation it is the 30th largest of 129 generating plants in the state.

Wild Horse within Washington, 2025
MeasureThis plantWashingtonShare
Capacity (MW)27331,7120.9%
Generation (MWh)590,982101,512,8620.6%
Wind capacity (MW)2733,3878.0%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Wild Horse plant, and when do they retire?

3 operable generators total 273 MW, with an average age of 19 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2000s3273100%none reported
Every generator, 3 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingOnshore Wind Turbine2292006n/a
WHS1OperatingSolar Photovoltaic12007n/a
WH2OperatingOnshore Wind Turbine442009n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Wild Horse plant?

EIA lists no joint owners for Wild Horse. Puget Sound Energy Inc operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Puget Sound Energy Inc charge homes?

Puget Sound Energy Inc, the operator of Wild Horse, had an average residential price of 17.01¢ per kWh and an average bill of $147 a month in 2025, 29% above the Washington average of 13.17¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Washington
Puget Sound Energy Inc17.01¢$14729% higher
Washington average13.17¢$124
U.S. average17.23¢$15131% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

What fuels does the Wild Horse plant use?

Wild Horse has capacity on 2 fuels: 100% wind and 0% solar. In 2025, wind made 100% of its output.

Capacity and 2025 generation by fuel
FuelMWShare2025 MWh
Wind27399.8%590,306
Solar10.2%676

Source: EIA Forms EIA-860 and EIA-923, 2025.

Where is the Wild Horse plant?

Wild Horse is in Ellensburg, Kittitas County, Washington, at 47.0363° N, 120.2065° W. It sits in the Puget Sound Energy balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in Washington are similar in size?

Washington has 23 operable wind plants with 3,387 MW of capacity, and Wild Horse's 273 MW is 8% of that.

Wind plants in Washington around this size
PlantCountyMW2025 MWh
Lower Snake River Wind Energy ProjectGarfield343795,345
Wild HorseKittitas273590,306
Tucannon River Wind FarmColumbia267736,786
Windy Flats Wind ProjectKlickitat262650,866
Marengo Wind PlantColumbia234612,625

Source: EIA Forms EIA-860 and EIA-923, 2025.