Solar power plant, Arizona
Agave solar power plant, Arizona
Agave is a 150 MW solar power plant in Maricopa County, Arizona, operated by Arizona Public Service Co, and it generated 297,844 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.3% of the generation reported in Arizona, and its capacity factor sits at the 46th percentile of U.S. solar plants. By 2025 generation it ranks 1,984th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Agave plant run compared with other solar plants?
The Agave plant had a capacity factor of 23% in 2025 on 150 MW of net summer capacity, the 46th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 83 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Agave | 23% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Agave plant generating more or less than last year?
Agave generated 297,844 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 6.2% ahead of the same months of 2025. 2024 has output for only 4 months, so the two years are not compared.
| Period | MWh |
|---|---|
| 2024 | 98,893 |
| 2025 | 297,844 |
| 2026 through August | 263,059 |
| 2025, same months | 247,650 |
Monthly generation, Sep 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 37,268 |
| July 2026 | 43,042 |
| June 2026 | 35,894 |
| May 2026 | 40,973 |
| April 2026 | 40,361 |
| March 2026 | 23,632 |
| February 2026 | 24,509 |
| January 2026 | 17,380 |
| December 2025 | 0 |
| November 2025 | 0 |
| October 2025 | 23,689 |
| September 2025 | 26,505 |
| August 2025 | 40,175 |
| July 2025 | 30,526 |
| June 2025 | 39,673 |
| May 2025 | 27,935 |
| April 2025 | 36,960 |
| March 2025 | 30,643 |
| February 2025 | 22,768 |
| January 2025 | 18,970 |
| December 2024 | 22,608 |
| November 2024 | 25,979 |
| October 2024 | 11,054 |
| September 2024 | 39,252 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Agave plant, and when do they retire?
1 operable generator totals 150 MW, with an average age of 2 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860. 1 more is proposed, totalling 150 MW.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 150 | 100% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| A150M | Operating | Solar Photovoltaic | 150 | 2023 | n/a |
| A400M | Built, not yet operating | Batteries | 150 | 2026 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Agave plant?
EIA lists no joint owners for Agave. Arizona Public Service Co operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What does Arizona Public Service Co charge homes?
Arizona Public Service Co, the operator of Agave, had an average residential price of 17.03¢ per kWh and an average bill of $165 a month in 2025, 12% above the Arizona average of 15.26¢.
| Measure | Price | Monthly bill | Against Arizona |
|---|---|---|---|
| Arizona Public Service Co | 17.03¢ | $165 | 12% higher |
| Arizona average | 15.26¢ | $157 | |
| U.S. average | 17.23¢ | $151 | 13% higher |
Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.
Where is the Agave plant?
Agave is in Arlington, Maricopa County, Arizona, at 33.3239° N, 112.8397° W. It sits in the Arizona Public Service Company balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Arizona are similar in size?
Arizona has 111 operable solar plants with 6,672 MW of capacity, and Agave's 150 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Mesquite Solar 3, LLC | Maricopa | 150 | 443,395 |
| Sun Streams 2 | Maricopa | 150 | 328,214 |
| Harquahala Sun Solar Project | Maricopa | 150 | 316,758 |
| Agave | Maricopa | 150 | 297,844 |
| Wilmot Energy Center LLC | Pima | 130 | 271,021 |
| Arlington Valley Solar Energy II | Maricopa | 129 | 335,989 |
| Storey Solar and Storage | Pinal | 122 | 314,336 |
Source: EIA Forms EIA-860 and EIA-923, 2025.