Wind power plant, California
Alta Wind X power plant, California
Alta Wind X is a 138 MW wind power plant in Kern County, California, operated by Alta Wind X, LLC, and it generated 361,130 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in California, and its capacity factor sits at the 38th percentile of U.S. wind plants. By 2025 generation it ranks 1,733rd of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Alta Wind X plant run compared with other wind plants?
The Alta Wind X plant had a capacity factor of 30% in 2025 on 138 MW of net summer capacity, the 38th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 109 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Alta Wind X | 30% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Alta Wind X plant generating more or less than last year?
Generation at Alta Wind X fell 4.7% from 2024 to 2025, from 379,046 MWh to 361,130 MWh.
| Period | MWh |
|---|---|
| 2024 | 379,046 |
| 2025 | 361,130 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 15,096 |
| November 2025 | 12,727 |
| October 2025 | 23,268 |
| September 2025 | 25,464 |
| August 2025 | 39,379 |
| July 2025 | 42,244 |
| June 2025 | 41,464 |
| May 2025 | 42,208 |
| April 2025 | 42,459 |
| March 2025 | 35,718 |
| February 2025 | 23,609 |
| January 2025 | 17,494 |
| December 2024 | 16,847 |
| November 2024 | 19,350 |
| October 2024 | 27,637 |
| September 2024 | 27,450 |
| August 2024 | 37,417 |
| July 2024 | 34,790 |
| June 2024 | 42,598 |
| May 2024 | 48,431 |
| April 2024 | 40,662 |
| March 2024 | 38,297 |
| February 2024 | 20,461 |
| January 2024 | 25,106 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Alta Wind X plant, and when do they retire?
1 operable generator totals 138 MW, with an average age of 11 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 138 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| AW10 | Operating | Onshore Wind Turbine | 138 | 2014 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Alta Wind X plant?
NRG Renew is the only joint owner reported for Alta Wind X, with 100.0%. Alta Wind X, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Alta Wind X plant?
Alta Wind X is in Mojave, Kern County, California, at 35.0600° N, 118.2000° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in California are similar in size?
California has 111 operable wind plants with 6,479 MW of capacity, and Alta Wind X's 138 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Mustang Hills LLC | Kern | 150 | 267,144 |
| Alta Wind VIII | Kern | 150 | 219,153 |
| Tule Wind LLC | San Diego | 143 | 365,139 |
| Alta Wind X | Kern | 138 | 361,130 |
| Pine Tree Wind Power Project | Kern | 135 | 123,003 |
| Pinyon Pine II | Kern | 132 | 204,303 |
| Voyager Wind I | Kern | 131 | 388,903 |
Source: EIA Forms EIA-860 and EIA-923, 2025.