AP North Lake I, LP is a 20 MW solar power plant in Riverside County, California, operated by AP North Lake I, LP, and it generated 45,684 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 84th percentile of U.S. solar plants. By 2025 generation it ranks 4,206th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the AP North Lake I, LP plant run compared with other solar plants?
The AP North Lake I, LP plant had a capacity factor of 28% in 2025 on 18.5 MW of net summer capacity, the 84th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 103 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| AP North Lake I, LP | 28% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the AP North Lake I, LP plant generating more or less than last year?
Generation at AP North Lake I, LP rose 15.2% from 2024 to 2025, from 39,644 MWh to 45,684 MWh.
| Period | MWh |
|---|---|
| 2024 | 39,644 |
| 2025 | 45,684 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 2,168 |
| November 2025 | 2,425 |
| October 2025 | 3,628 |
| September 2025 | 3,886 |
| August 2025 | 4,792 |
| July 2025 | 5,657 |
| June 2025 | 5,127 |
| May 2025 | 4,749 |
| April 2025 | 4,189 |
| March 2025 | 3,637 |
| February 2025 | 2,956 |
| January 2025 | 2,470 |
| December 2024 | 2,106 |
| November 2024 | 2,534 |
| October 2024 | 3,305 |
| September 2024 | 3,300 |
| August 2024 | 4,203 |
| July 2024 | 4,616 |
| June 2024 | 4,289 |
| May 2024 | 4,460 |
| April 2024 | 4,034 |
| March 2024 | 2,920 |
| February 2024 | 1,930 |
| January 2024 | 1,947 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the AP North Lake I, LP plant, and when do they retire?
1 operable generator totals 20 MW, with an average age of 10 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 20 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| APNLI | Operating | Solar Photovoltaic | 20 | 2015 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the AP North Lake I, LP plant?
EIA lists no joint owners for AP North Lake I, LP. AP North Lake I, LP operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the AP North Lake I, LP plant?
AP North Lake I, LP is in Hemet, Riverside County, California, at 33.7400° N, 117.0106° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in California are similar in size?
California has 934 operable solar plants with 24,663 MW of capacity, and AP North Lake I, LP's 20 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Vega Solar | Merced | 20 | 49,280 |
| Nicolis Solar PV Plant | Tulare | 20 | 46,346 |
| Maricopa West Solar PV, LLC | Kern | 20 | 50,290 |
| AP North Lake I, LP | Riverside | 20 | 45,684 |
| Kettleman Solar -Centaurus | Kings | 20 | 42,914 |
| Coronal Lost Hills | Kern | 20 | 35,431 |
| Imperial Valley Solar Co (IVSC) 2, LLC | Imperial | 20 | 43,887 |
Source: EIA Forms EIA-860 and EIA-923, 2025.