Bellingham Cogeneration Facility is a 386 MW natural gas power plant in Norfolk County, Massachusetts, operated by Northeast Energy Associates LP, and it generated 318,165 MWh in 2025 (Forms EIA-860 and EIA-923). That is 1.4% of the generation reported in Massachusetts, and its capacity factor sits at the 40th percentile of U.S. natural gas plants. By 2025 generation it ranks 1,900th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Bellingham Cogeneration Facility plant run compared with other natural gas plants?
The Bellingham Cogeneration Facility plant had a capacity factor of 13% in 2025 on 264 MW of net summer capacity, the 40th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 48 days at full output out of 365.
0%Shaded: the middle half of natural gas plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Bellingham Cogeneration Facility | 13% |
| Natural gas plants, 75th percentile | 56% |
| Natural gas plants, median | 22% |
| Natural gas plants, 25th percentile | 6% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Bellingham Cogeneration Facility plant generating more or less than last year?
Bellingham Cogeneration Facility generated 318,165 MWh in 2025; EIA reports no 2024 total to compare. 2024 has output for only 8 months, so the two years are not compared.
| Period | MWh |
|---|---|
| 2024 | 367,825 |
| 2025 | 318,165 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 12,584 |
| November 2025 | 29,742 |
| October 2025 | 26,294 |
| September 2025 | 3,671 |
| August 2025 | 78,485 |
| July 2025 | 136,264 |
| June 2025 | 19,337 |
| May 2025 | 5,330 |
| April 2025 | 937 |
| March 2025 | 0 |
| February 2025 | 638 |
| January 2025 | 4,883 |
| December 2024 | 1,316 |
| November 2024 | 45,469 |
| October 2024 | 27,642 |
| September 2024 | 22 |
| August 2024 | 107,121 |
| July 2024 | 162,217 |
| June 2024 | 23,166 |
| May 2024 | 0 |
| April 2024 | 872 |
| March 2024 | 0 |
| February 2024 | 0 |
| January 2024 | 0 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Bellingham Cogeneration Facility plant, and when do they retire?
3 operable generators total 386 MW, with an average age of 34 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1990s | 3 | 386 | 100% | none reported |
Every generator, 3 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| CT1 | Operating | Natural Gas Fired Combined Cycle | 129 | 1991 | n/a |
| CT2 | Operating | Natural Gas Fired Combined Cycle | 129 | 1991 | n/a |
| ST1 | Operating | Natural Gas Fired Combined Cycle | 129 | 1991 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Bellingham Cogeneration Facility plant?
EIA lists no joint owners for Bellingham Cogeneration Facility. Northeast Energy Associates LP operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Bellingham Cogeneration Facility plant?
Bellingham Cogeneration Facility is in Bellingham, Norfolk County, Massachusetts, at 42.0925° N, 71.4833° W. It sits in the ISO New England Inc. balancing area (NERC region NPCC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which natural gas plants in Massachusetts are similar in size?
Massachusetts has 40 operable natural gas plants with 5,978 MW of capacity, and Bellingham Cogeneration Facility's 386 MW is 6% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| ANP Bellingham Energy Project | Norfolk | 578 | 3,509,349 |
| ANP Blackstone Energy Project | Worcester | 578 | 3,254,404 |
| Millennium Power | Worcester | 428 | 852,182 |
| Bellingham Cogeneration Facility | Norfolk | 386 | 304,572 |
| Berkshire Power | Hampden | 289 | 809,512 |
| Exelon West Medway II LLC | Norfolk | 264 | 205,340 |
| Masspower | Hampden | 261 | 441,701 |
Source: EIA Forms EIA-860 and EIA-923, 2025.