Solar power plant, Texas

Bernard Creek Solar power plant, Texas

Bernard Creek Solar is a 230 MW solar power plant in Wharton County, Texas, operated by Bernard Creek Solar, LLC, and it generated 500,378 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Texas, and its capacity factor sits at the 63rd percentile of U.S. solar plants. By 2025 generation it ranks 1,337th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

230 MWNameplate capacity
25%Capacity factor, 2025, 63rd percentile, on 230 MW net summer
0.1%Of TX generation, 2025
2 yearsAverage generator age, by MW

How hard does the Bernard Creek Solar plant run compared with other solar plants?

The Bernard Creek Solar plant had a capacity factor of 25% in 2025 on 230 MW of net summer capacity, the 63rd percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 91 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Bernard Creek Solar25%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Bernard Creek Solar plant generating more or less than last year?

Generation at Bernard Creek Solar rose 17.4% from 2024 to 2025, from 426,340 MWh to 500,378 MWh. Through August 2026 it is running 1.2% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024426,340
2025500,378
2026 through August356,780
2025, same months352,666
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202655,926
July 202654,908
June 202649,309
May 202650,061
April 202633,176
March 202644,498
February 202638,023
January 202630,879
December 202524,724
November 202533,910
October 202542,132
September 202546,946
August 202548,429
July 202550,397
June 202550,815
May 202552,523
April 202545,739
March 202549,469
February 202528,715
January 202526,579
December 202425,701
November 202429,634
October 202443,736
September 202438,449
August 202451,518
July 202440,289
June 202435,944
May 202436,280
April 202432,514
March 202433,971
February 202431,646
January 202426,658

Source: EIA Form EIA-923, through August 2026.

How much of Texas' electricity comes from the Bernard Creek Solar plant?

Bernard Creek Solar made 0.1% of the 592,896,176 MWh reported by Texas plants in 2025, from 0.1% of the state's 195,966 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 246th largest of 1,023 plants in Texas, the 1,359th largest of 14,327 in the U.S. and the 122nd largest of 7,223 solar plants. By 2025 generation it is the 283rd largest of 816 generating plants in the state.

Bernard Creek Solar within Texas, 2025
MeasureThis plantTexasShare
Capacity (MW)230195,9660.1%
Generation (MWh)500,378592,896,1760.1%
Solar capacity (MW)23030,7390.7%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Bernard Creek Solar plant, and when do they retire?

1 operable generator totals 230 MW, with an average age of 2 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1230100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
CSBS1OperatingSolar Photovoltaic2302023n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Bernard Creek Solar plant?

EIA lists no joint owners for Bernard Creek Solar. Bernard Creek Solar, LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Bernard Creek Solar plant?

Bernard Creek Solar is in Hungerford, Wharton County, Texas, at 29.4553° N, 96.0883° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Texas are similar in size?

Texas has 225 operable solar plants with 30,739 MW of capacity, and Bernard Creek Solar's 230 MW is 1% of that.

Solar plants in Texas around this size
PlantCountyMW2025 MWh
Eiffel Solar ProjectLamar240573,603
True North Solar, LLCFalls239556,356
Fence Post Solar Hybrid Project, LLCNavarro236528,457
Bernard Creek SolarWharton230500,378
Fighting Jays Solar ProjectFort Bend228454,185
ENGIE Long Draw Solar LLCBorden225519,379
Azure Sky SolarHaskell225544,713

Source: EIA Forms EIA-860 and EIA-923, 2025.