Big Bend 1 Solar and Battery Storage is a 32.4 MW power plant, 19.8 MW of it solar, in Hillsborough County, Florida, operated by Tampa Electric Co, and it generated 2,223 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 2nd percentile of U.S. solar plants. By 2025 generation it ranks 10,426th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

32.4 MWNameplate capacity
1%Capacity factor, 2025, solar units, 2nd percentile, on 19.8 MW net summer
10,426thU.S. rank by generation, 2025
7 yearsAverage generator age, by MW

How hard does the Big Bend 1 Solar and Battery Storage plant run compared with other solar plants?

The Big Bend 1 Solar and Battery Storage plant's solar units had a capacity factor of 1% in 2025 on 19.8 MW of net summer capacity, the 2nd percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 5 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Big Bend 1 Solar and Battery Storage1%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its solar generators only. Values above 105% are left out of the comparison.

Is the Big Bend 1 Solar and Battery Storage plant generating more or less than last year?

Big Bend 1 Solar and Battery Storage generated 2,223 MWh in 2025; EIA reports no 2024 total to compare.

Net generation by period
PeriodMWh
2024n/a
20252,223
2026 through August26,121
Monthly generation, Dec 2025 to Aug 2026
MonthMWh
August 20262,669
July 20263,383
June 20264,145
May 20263,263
April 20263,758
March 20263,752
February 20262,724
January 20262,427
December 20252,223

Source: EIA Form EIA-923, through August 2026.

How much of Florida's electricity comes from the Big Bend 1 Solar and Battery Storage plant?

Big Bend 1 Solar and Battery Storage made 0.0% of the 267,867,735 MWh reported by Florida plants in 2025, from 0.0% of the state's 79,936 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 250th largest of 331 plants in Florida, the 4,295th largest of 14,327 in the U.S. and the 1,304th largest of 7,223 solar plants on its solar units alone. By 2025 generation it is the 297th largest of 313 generating plants in the state.

Big Bend 1 Solar and Battery Storage within Florida, 2025
MeasureThis plantFloridaShare
Capacity (MW)3279,9360.0%
Generation (MWh)2,223267,867,7350.0%
Solar capacity (MW)2012,2230.2%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Big Bend 1 Solar and Battery Storage plant, and when do they retire?

2 operable generators total 32.4 MW, with an average age of 7 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s232100%none reported
Every generator, 2 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingSolar Photovoltaic202017n/a
BESS1OperatingBatteries132019n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Big Bend 1 Solar and Battery Storage plant?

EIA lists no joint owners for Big Bend 1 Solar and Battery Storage. Tampa Electric Co operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Tampa Electric Co charge homes?

Tampa Electric Co, the operator of Big Bend 1 Solar and Battery Storage, had an average residential price of 17.32¢ per kWh and an average bill of $194 a month in 2025, 14% above the Florida average of 15.21¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Florida
Tampa Electric Co17.32¢$19414% higher
Florida average15.21¢$168
U.S. average17.23¢$15113% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

What fuels does the Big Bend 1 Solar and Battery Storage plant use?

Big Bend 1 Solar and Battery Storage has capacity on 2 fuels: 61% solar and 39% battery and pumped storage. In 2025, solar made 101% of its output.

Capacity and 2025 generation by fuel
FuelMWShare2025 MWh
Solar2061.1%2,239
Battery and pumped storage1338.9%-16

Source: EIA Forms EIA-860 and EIA-923, 2025.

Where is the Big Bend 1 Solar and Battery Storage plant?

Big Bend 1 Solar and Battery Storage is in Apollo Beach, Hillsborough County, Florida, at 27.7853° N, 82.3847° W. It sits in the Tampa Electric Company balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Florida are similar in size?

Florida has 210 operable solar plants with 12,223 MW of capacity, and Big Bend 1 Solar and Battery Storage's 19.8 MW is 0% of that.

Solar plants in Florida around this size
PlantCountyMW2025 MWh
Dover Solar and Battery StorageHillsborough2547,890
English Creek SolarHillsborough2353,276
CoTAL Solar FarmLeon2038,046
Big Bend 1 Solar and Battery StorageHillsborough202,239
Jacksonville SolarDuval138,753
Space Coast Next Gen Solar EnergyBrevard1010,502

Source: EIA Forms EIA-860 and EIA-923, 2025.