Skip to main content
RateWatt

Solar power plant, Florida

Blue Heron Solar power plant, Florida

Blue Heron Solar is a 74.5 MW solar power plant in Hendry County, Florida, operated by Florida Power & Light Co, and it generated 154,302 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Florida, and its capacity factor sits at the 54th percentile of U.S. solar plants. By 2025 generation it ranks 2,857th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

74.5 MWNameplate capacity
24%Capacity factor, 2025, 54th percentile, on 74.5 MW net summer
0.1%Of FL generation, 2025
5 yearsAverage generator age, by MW

How hard does the Blue Heron Solar plant run compared with other solar plants?

The Blue Heron Solar plant had a capacity factor of 24% in 2025 on 74.5 MW of net summer capacity, the 54th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 86 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Blue Heron Solar24%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Blue Heron Solar plant generating more or less than last year?

Generation at Blue Heron Solar rose 5.1% from 2024 to 2025, from 146,782 MWh to 154,302 MWh. Through August 2026 it is running 3.2% behind the same months of 2025.

Net generation by period
PeriodMWh
2024146,782
2025154,302
2026 through August101,887
2025, same months105,237
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202613,550
July 202613,454
June 202612,763
May 202614,192
April 202614,487
March 202613,449
February 20269,709
January 202610,283
December 202512,014
November 202512,027
October 202512,978
September 202512,046
August 202512,677
July 202513,363
June 202512,315
May 202513,848
April 202515,648
March 202515,040
February 202511,618
January 202510,728
December 202411,905
November 202411,758
October 202411,173
September 202411,590
August 202412,055
July 202411,981
June 202411,652
May 202415,024
April 202414,300
March 202413,209
February 202413,148
January 20248,987

Source: EIA Form EIA-923, through August 2026.

How much of Florida's electricity comes from the Blue Heron Solar plant?

Blue Heron Solar made 0.1% of the 267,867,735 MWh reported by Florida plants in 2025, from 0.1% of the state's 79,936 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 105th largest of 331 plants in Florida, the 3,163rd largest of 14,327 in the U.S. and the 647th largest of 7,223 solar plants. By 2025 generation it is the 146th largest of 313 generating plants in the state.

Blue Heron Solar within Florida, 2025
MeasureThis plantFloridaShare
Capacity (MW)7579,9360.1%
Generation (MWh)154,302267,867,7350.1%
Solar capacity (MW)7512,2230.6%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Blue Heron Solar plant, and when do they retire?

1 operable generator totals 74.5 MW, with an average age of 5 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s175100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingSolar Photovoltaic752020n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Blue Heron Solar plant?

EIA lists no joint owners for Blue Heron Solar. Florida Power & Light Co operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Florida Power & Light Co charge homes?

Florida Power & Light Co, the operator of Blue Heron Solar, had an average residential price of 14.62¢ per kWh and an average bill of $162 a month in 2025, 4% below the Florida average of 15.21¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Florida
Florida Power & Light Co14.62¢$1624% lower
Florida average15.21¢$168
U.S. average17.23¢$15113% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Blue Heron Solar plant?

Blue Heron Solar is in Clewiston, Hendry County, Florida, at 26.7016° N, 81.1292° W. It sits in the Florida Power & Light Company balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Florida are similar in size?

Florida has 210 operable solar plants with 12,223 MW of capacity, and Blue Heron Solar's 74.5 MW is 1% of that.

Solar plants in Florida around this size
PlantCountyMW2025 MWh
Okeechobee SolarOkeechobee75149,162
Southfork SolarManatee75144,690
Debary Solar Power PlantVolusia75126,812
Blue Heron SolarHendry75154,302
Cattle RanchDeSoto75146,676
Twin LakesPutnam75122,507
Babcock PreserveCharlotte75151,839

Source: EIA Forms EIA-860 and EIA-923, 2025.