Wind power plant, New Mexico
Borderlands Wind, LLC power plant, New Mexico
Borderlands Wind, LLC is a 100 MW wind power plant in Catron County, New Mexico, operated by Borderlands Wind, LLC, and it generated 252,062 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.6% of the generation reported in New Mexico, and its capacity factor sits at the 34th percentile of U.S. wind plants. By 2025 generation it ranks 2,221st of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Borderlands Wind, LLC plant run compared with other wind plants?
The Borderlands Wind, LLC plant had a capacity factor of 29% in 2025 on 100 MW of net summer capacity, the 34th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 105 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Borderlands Wind, LLC | 29% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Borderlands Wind, LLC plant generating more or less than last year?
Generation at Borderlands Wind, LLC fell 0.9% from 2024 to 2025, from 254,465 MWh to 252,062 MWh. Through August 2026 it is running 12.8% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 254,465 |
| 2025 | 252,062 |
| 2026 through August | 163,559 |
| 2025, same months | 187,469 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 11,155 |
| July 2026 | 11,396 |
| June 2026 | 25,713 |
| May 2026 | 24,415 |
| April 2026 | 30,234 |
| March 2026 | 24,018 |
| February 2026 | 20,647 |
| January 2026 | 15,981 |
| December 2025 | 18,410 |
| November 2025 | 14,207 |
| October 2025 | 17,085 |
| September 2025 | 14,891 |
| August 2025 | 15,812 |
| July 2025 | 16,476 |
| June 2025 | 21,497 |
| May 2025 | 27,156 |
| April 2025 | 24,975 |
| March 2025 | 30,038 |
| February 2025 | 26,721 |
| January 2025 | 24,794 |
| December 2024 | 20,683 |
| November 2024 | 20,974 |
| October 2024 | 19,560 |
| September 2024 | 17,725 |
| August 2024 | 13,845 |
| July 2024 | 18,030 |
| June 2024 | 16,470 |
| May 2024 | 25,408 |
| April 2024 | 23,504 |
| March 2024 | 28,710 |
| February 2024 | 24,791 |
| January 2024 | 24,765 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Borderlands Wind, LLC plant, and when do they retire?
1 operable generator totals 100 MW, with an average age of 4 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 100 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| WBB | Operating | Onshore Wind Turbine | 100 | 2021 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Borderlands Wind, LLC plant?
EIA lists no joint owners for Borderlands Wind, LLC. Borderlands Wind, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Borderlands Wind, LLC plant?
Borderlands Wind, LLC is in Quemado, Catron County, New Mexico, at 34.1598° N, 108.8945° W. It sits in the Tucson Electric Power Company balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in New Mexico are similar in size?
New Mexico has 29 operable wind plants with 4,429 MW of capacity, and Borderlands Wind, LLC's 100 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Red Mesa Wind LLC | Sandoval | 102 | 163,235 |
| Caprock Wind Farm | Quay | 100 | 378,712 |
| High Lonesome Mesa LLC | Torrance | 100 | 313,427 |
| Borderlands Wind, LLC | Catron | 100 | 252,062 |
| Casa Mesa Wind Energy Center Hybrid | Quay | 51 | 180,107 |
| Macho Springs Power I | Luna | 50 | 115,304 |
| Milo Wind Project LLC | Roosevelt | 50 | 183,452 |
Source: EIA Forms EIA-860 and EIA-923, 2025.