Calderwood is a 157 MW hydro power plant in Blount County, Tennessee, operated by Brookfield Smoky Mountain Hydropower LP, and it generated 568,694 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.8% of the generation reported in Tennessee, and its capacity factor sits at the 70th percentile of U.S. hydro plants. By 2025 generation it ranks 1,188th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Calderwood plant run compared with other hydro plants?
The Calderwood plant had a capacity factor of 42% in 2025 on 156 MW of net summer capacity, the 70th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 152 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Calderwood | 42% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Calderwood plant generating more or less than last year?
Generation at Calderwood rose 3.5% from 2024 to 2025, from 549,247 MWh to 568,694 MWh.
| Period | MWh |
|---|---|
| 2024 | 549,247 |
| 2025 | 568,694 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 32,383 |
| November 2025 | 38,411 |
| October 2025 | 52,777 |
| September 2025 | 53,869 |
| August 2025 | 49,656 |
| July 2025 | 37,895 |
| June 2025 | 52,862 |
| May 2025 | 63,517 |
| April 2025 | 27,084 |
| March 2025 | 41,647 |
| February 2025 | 60,324 |
| January 2025 | 58,269 |
| December 2024 | 50,183 |
| November 2024 | 40,853 |
| October 2024 | 73,727 |
| September 2024 | 36,770 |
| August 2024 | 34,540 |
| July 2024 | 30,422 |
| June 2024 | 44,945 |
| May 2024 | 26,645 |
| April 2024 | 6,320 |
| March 2024 | 56,649 |
| February 2024 | 74,881 |
| January 2024 | 73,312 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Calderwood plant, and when do they retire?
3 operable generators total 157 MW, with an average age of 92 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1930s | 3 | 157 | 100% | none reported |
Every generator, 3 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Conventional Hydroelectric | 52 | 1930 | n/a |
| 2 | Operating | Conventional Hydroelectric | 52 | 1930 | n/a |
| 3 | Operating | Conventional Hydroelectric | 52 | 1938 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Calderwood plant?
EIA lists no joint owners for Calderwood. Brookfield Smoky Mountain Hydropower LP operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Calderwood plant?
Calderwood is in Tallassee, Blount County, Tennessee, at 35.4923° N, 83.9806° W. It sits in the Tennessee Valley Authority balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which hydro plants in Tennessee are similar in size?
Tennessee has 28 operable hydro plants with 2,520 MW of capacity, and Calderwood's 157 MW is 6% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Pickwick Landing Dam | Hardin | 240 | 1,294,568 |
| Watts Bar Hydro | Rhea | 175 | 865,430 |
| Chickamauga | Hamilton | 160 | 693,812 |
| Calderwood | Blount | 157 | 568,694 |
| Center Hill | DeKalb | 156 | 355,792 |
| Fort Loudoun | Loudon | 153 | 633,112 |
| Douglas Dam | Sevier | 151 | 341,251 |
Source: EIA Forms EIA-860 and EIA-923, 2025.