Nuclear power plant, Missouri

Callaway nuclear power plant, Missouri

Callaway is a 1,236 MW nuclear power plant in Callaway County, Missouri, operated by Union Electric Co-(MO), and it generated 7,116,161 MWh in 2025 (Forms EIA-860 and EIA-923). That is 10.0% of the generation reported in Missouri, and its capacity factor sits at the 2nd percentile of U.S. nuclear plants. By 2025 generation it ranks 128th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

1,236 MWNameplate capacity
68%Capacity factor, 2025, 2nd percentile, on 1,190 MW net summer
10.0%Of MO generation, 2025
41 yearsAverage generator age, by MW

How hard does the Callaway plant run compared with other nuclear plants?

The Callaway plant had a capacity factor of 68% in 2025 on 1,190 MW of net summer capacity, the 2nd percentile of the 54 U.S. nuclear plants with at least 20 MW. The typical nuclear plant reached 95%. That equals about 249 days at full output out of 365.

0%Shaded: the middle half of nuclear plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Callaway68%
Nuclear plants, 75th percentile97%
Nuclear plants, median95%
Nuclear plants, 25th percentile90%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Callaway plant generating more or less than last year?

Generation at Callaway fell 32.4% from 2024 to 2025, from 10,525,784 MWh to 7,116,161 MWh. Through August 2026 it is running 71.8% ahead of the same months of 2025.

Net generation by period
PeriodMWh
202410,525,784
20257,116,161
2026 through August7,099,478
2025, same months4,132,108
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 2026892,366
July 2026889,020
June 2026865,289
May 2026906,157
April 2026879,094
March 2026912,298
February 2026831,349
January 2026923,905
December 2025883,612
November 2025325,615
October 2025908,244
September 2025866,582
August 2025895,345
July 2025661,130
June 20250
May 20250
April 20250
March 2025818,442
February 2025839,632
January 2025917,559
December 2024923,349
November 2024887,341
October 2024909,559
September 2024871,405
August 2024893,974
July 2024890,370
June 2024864,887
May 2024904,397
April 2024883,381
March 2024920,500
February 2024652,086
January 2024924,535

Source: EIA Form EIA-923, through August 2026.

How much of Missouri's electricity comes from the Callaway plant?

Callaway made 10.0% of the 71,443,096 MWh reported by Missouri plants in 2025, from 5.3% of the state's 23,215 MW of capacity. Its share of output is 1.9 times its share of capacity. By capacity it is the 4th largest of 137 plants in Missouri, the 210th largest of 14,327 in the U.S. and the 40th largest of 56 nuclear plants. By 2025 generation it is the 2nd largest of 122 generating plants in the state.

Callaway within Missouri, 2025
MeasureThis plantMissouriShare
Capacity (MW)1,23623,2155.3%
Generation (MWh)7,116,16171,443,09610.0%
Nuclear capacity (MW)1,2361,236100.0%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Callaway plant, and when do they retire?

1 operable generator totals 1,236 MW, with an average age of 41 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1980s11,236100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingNuclear1,2361984n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Callaway plant?

EIA lists no joint owners for Callaway. Union Electric Co-(MO) operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Union Electric Co charge homes?

Union Electric Co, the operator of Callaway, had an average residential price of 13.27¢ per kWh and an average bill of $137 a month in 2025, about the same as the Missouri average of 13.30¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Missouri
Union Electric Co13.27¢$137about the same
Missouri average13.30¢$138
U.S. average17.23¢$15130% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Callaway plant?

Callaway is in Fulton, Callaway County, Missouri, at 38.7589° N, 91.7788° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which Missouri power plants are similar in size?

Callaway is the only operable nuclear plant in Missouri, so these are the plants of any fuel closest to its 1,236 MW.

Power plants in Missouri around this size
PlantFuelCountyMW2025 MWh
LabadieCoalFranklin2,38916,728,972
IatanCoalPlatte1,7545,774,937
New MadridCoalNew Madrid1,3006,738,552
CallawayNuclearCallaway1,2367,116,161
Thomas HillCoalRandolph1,1826,938,209
SiouxCoalSt Charles1,0993,986,364
HawthornCoalJackson1,0463,018,236

Source: EIA Forms EIA-860 and EIA-923, 2025.