Hydro power plant, Oregon
Carmen Smith hydroelectric power plant, Oregon
Carmen Smith is a 114 MW hydro power plant in Linn County, Oregon, operated by Eugene Water & Electric Board, and it generated 167,869 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.3% of the generation reported in Oregon, and its capacity factor sits at the 17th percentile of U.S. hydro plants. By 2025 generation it ranks 2,735th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Carmen Smith plant run compared with other hydro plants?
The Carmen Smith plant had a capacity factor of 18% in 2025 on 104 MW of net summer capacity, the 17th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 67 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Carmen Smith | 18% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Carmen Smith plant generating more or less than last year?
Generation at Carmen Smith fell 24.8% from 2024 to 2025, from 223,304 MWh to 167,869 MWh.
| Period | MWh |
|---|---|
| 2024 | 223,304 |
| 2025 | 167,869 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 14,400 |
| November 2025 | 9,674 |
| October 2025 | 6,500 |
| September 2025 | 7,334 |
| August 2025 | 10,884 |
| July 2025 | 10,172 |
| June 2025 | 902 |
| May 2025 | 18,778 |
| April 2025 | 20,752 |
| March 2025 | 25,704 |
| February 2025 | 18,196 |
| January 2025 | 24,573 |
| December 2024 | 26,175 |
| November 2024 | 15,486 |
| October 2024 | 7,600 |
| September 2024 | 8,177 |
| August 2024 | 12,290 |
| July 2024 | 15,721 |
| June 2024 | 19,386 |
| May 2024 | 26,440 |
| April 2024 | 22,360 |
| March 2024 | 23,830 |
| February 2024 | 24,041 |
| January 2024 | 21,798 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Carmen Smith plant, and when do they retire?
3 operable generators total 114 MW, with an average age of 62 years weighted by capacity at the end of 2025. 9.9 MW, 9% of operable capacity, has a planned retirement, the first in 2030.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1960s | 3 | 114 | 100% | 2030 |
| Year | Units | MW retiring | Share of plant |
|---|---|---|---|
| 2030 | 1 | 10 | 9% |
Every generator, 3 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Out of service, returning | Conventional Hydroelectric | 52 | 1963 | n/a |
| 2 | Operating | Conventional Hydroelectric | 52 | 1963 | n/a |
| 3 | Operating | Conventional Hydroelectric | 10 | 1963 | 2030 |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Carmen Smith plant?
EIA lists no joint owners for Carmen Smith. Eugene Water & Electric Board operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Carmen Smith plant?
Carmen Smith is in McKenzie Bridge, Linn County, Oregon, at 44.2860° N, 122.0414° W. It sits in the Bonneville Power Administration balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which hydro plants in Oregon are similar in size?
Oregon has 63 operable hydro plants with 8,360 MW of capacity, and Carmen Smith's 114 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Oxbow (OR) | Baker | 190 | 990,285 |
| Lookout Point | Lane | 120 | 227,034 |
| Carmen Smith | Linn | 114 | 167,869 |
| Pelton | Jefferson | 110 | 399,648 |
| Detroit | Marion | 100 | 226,867 |
| Green Peter | Linn | 80 | 115,585 |
Source: EIA Forms EIA-860 and EIA-923, 2025.