Hydro power plant, Oregon
Lookout Point hydroelectric power plant, Oregon
Lookout Point is a 120 MW hydro power plant in Lane County, Oregon, operated by USACE Northwestern Division, and it generated 227,034 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.4% of the generation reported in Oregon, and its capacity factor sits at the 25th percentile of U.S. hydro plants. By 2025 generation it ranks 2,333rd of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Lookout Point plant run compared with other hydro plants?
The Lookout Point plant had a capacity factor of 22% in 2025 on 120 MW of net summer capacity, the 25th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 79 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Lookout Point | 22% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Lookout Point plant generating more or less than last year?
Lookout Point generated 227,034 MWh in 2025; EIA reports no 2024 total to compare. 2024 has output for only 9 months, so the two years are not compared.
4 months show net generation below zero, when the plant used more power than it sent out, so the months are listed below rather than charted.
| Period | MWh |
|---|---|
| 2024 | 175,058 |
| 2025 | 227,034 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 1,926 |
| November 2025 | -94 |
| October 2025 | 7,665 |
| September 2025 | 8,459 |
| August 2025 | 12,974 |
| July 2025 | 18,309 |
| June 2025 | 12,058 |
| May 2025 | 44,174 |
| April 2025 | 15,490 |
| March 2025 | 20,377 |
| February 2025 | 14,363 |
| January 2025 | 71,333 |
| December 2024 | -130 |
| November 2024 | -97 |
| October 2024 | -72 |
| September 2024 | 269 |
| August 2024 | 8,970 |
| July 2024 | 37,394 |
| June 2024 | 19,229 |
| May 2024 | 16,998 |
| April 2024 | 8,023 |
| March 2024 | 4,977 |
| February 2024 | 41,737 |
| January 2024 | 37,760 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Lookout Point plant, and when do they retire?
3 operable generators total 120 MW, with an average age of 70 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1950s | 3 | 120 | 100% | none reported |
Every generator, 3 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Conventional Hydroelectric | 40 | 1955 | n/a |
| 2 | Operating | Conventional Hydroelectric | 40 | 1955 | n/a |
| 3 | Operating | Conventional Hydroelectric | 40 | 1955 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Lookout Point plant?
EIA lists no joint owners for Lookout Point. USACE Northwestern Division operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Lookout Point plant?
Lookout Point is in Lowell, Lane County, Oregon, at 43.9153° N, 122.7531° W. It sits in the Bonneville Power Administration balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which hydro plants in Oregon are similar in size?
Oregon has 63 operable hydro plants with 8,360 MW of capacity, and Lookout Point's 120 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Oxbow (OR) | Baker | 190 | 990,285 |
| Lookout Point | Lane | 120 | 227,034 |
| Carmen Smith | Linn | 114 | 167,869 |
| Pelton | Jefferson | 110 | 399,648 |
| Detroit | Marion | 100 | 226,867 |