Wind power plant, Wyoming
Cedar Springs Wind IV power plant, Wyoming
Cedar Springs Wind IV is a 390 MW wind power plant in Converse County, Wyoming, operated by Cedar Springs Wind IV, LLC, and it generated 1,055,641 MWh in 2025 (Forms EIA-860 and EIA-923). That is 2.3% of the generation reported in Wyoming, and its capacity factor sits at the 43rd percentile of U.S. wind plants. By 2025 generation it ranks 711th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Cedar Springs Wind IV plant run compared with other wind plants?
The Cedar Springs Wind IV plant had a capacity factor of 31% in 2025 on 390 MW of net summer capacity, the 43rd percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 113 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Cedar Springs Wind IV | 31% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Cedar Springs Wind IV plant generating more or less than last year?
Cedar Springs Wind IV generated 1,055,641 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 42.1% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | n/a |
| 2025 | 1,055,641 |
| 2026 through August | 868,217 |
| 2025, same months | 610,996 |
Monthly generation, Jan 2025 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 71,352 |
| July 2026 | 62,908 |
| June 2026 | 98,747 |
| May 2026 | 101,558 |
| April 2026 | 108,765 |
| March 2026 | 134,496 |
| February 2026 | 124,718 |
| January 2026 | 165,673 |
| December 2025 | 165,551 |
| November 2025 | 104,030 |
| October 2025 | 102,632 |
| September 2025 | 72,432 |
| August 2025 | 65,019 |
| July 2025 | 73,850 |
| June 2025 | 66,241 |
| May 2025 | 96,255 |
| April 2025 | 101,053 |
| March 2025 | 136,077 |
| February 2025 | 63,787 |
| January 2025 | 8,714 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Cedar Springs Wind IV plant, and when do they retire?
1 operable generator totals 390 MW, with an average age of 0 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 390 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| CS4 | Operating | Onshore Wind Turbine | 390 | 2025 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Cedar Springs Wind IV plant?
EIA lists no joint owners for Cedar Springs Wind IV. Cedar Springs Wind IV, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Cedar Springs Wind IV plant?
Cedar Springs Wind IV is in Douglas, Converse County, Wyoming, at 43.1008° N, 105.7115° W. It sits in the Western Area Power Administration - Rocky Mountain Region balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Wyoming are similar in size?
Wyoming has 28 operable wind plants with 4,707 MW of capacity, and Cedar Springs Wind IV's 390 MW is 8% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Rock Creek Wind | Carbon | 590 | 212,181 |
| TB Flats | Carbon | 503 | 1,361,919 |
| Cedar Springs Wind IV | Converse | 390 | 1,055,641 |
| Boswell Wind | Albany | 330 | 1,184,619 |
| Ekola Flats | Carbon | 251 | 736,070 |
| Roundhouse Wind Energy Project | Laramie | 226 | 826,429 |
Source: EIA Forms EIA-860 and EIA-923, 2025.