Chevelon Butte Phase 2 wind power plant, Arizona

Chevelon Butte Phase 2 is a 216 MW wind power plant in Coconino County, Arizona, operated by AES Clean Energy, and it generated 525,472 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.5% of the generation reported in Arizona, and its capacity factor sits at the 32nd percentile of U.S. wind plants. By 2025 generation it ranks 1,295th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

216 MWNameplate capacity
28%Capacity factor, 2025, 32nd percentile, on 216 MW net summer
0.5%Of AZ generation, 2025
1 yearAverage generator age, by MW

How hard does the Chevelon Butte Phase 2 plant run compared with other wind plants?

The Chevelon Butte Phase 2 plant had a capacity factor of 28% in 2025 on 216 MW of net summer capacity, the 32nd percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 101 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Chevelon Butte Phase 228%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Chevelon Butte Phase 2 plant generating more or less than last year?

Chevelon Butte Phase 2 generated 525,472 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 12.0% behind the same months of 2025. 2024 has output for only 8 months, so the two years are not compared.

Net generation by period
PeriodMWh
2024297,481
2025525,472
2026 through August354,781
2025, same months403,083
Monthly generation, Apr 2024 to Aug 2026
MonthMWh
August 202634,448
July 202636,527
June 202669,419
May 202659,217
April 202659,468
March 202641,997
February 202630,616
January 202623,089
December 202528,815
November 202521,900
October 202534,779
September 202536,895
August 202544,496
July 202552,528
June 202550,749
May 202551,446
April 202548,742
March 202562,548
February 202552,062
January 202540,512
December 202426,482
November 202439,404
October 202429,949
September 202432,127
August 202430,331
July 202432,134
June 202449,836
May 202457,218
April 20240

Source: EIA Form EIA-923, through August 2026.

How much of Arizona's electricity comes from the Chevelon Butte Phase 2 plant?

Chevelon Butte Phase 2 made 0.5% of the 115,800,378 MWh reported by Arizona plants in 2025, from 0.5% of the state's 40,514 MW of capacity. By capacity it is the 46th largest of 191 plants in Arizona, the 1,417th largest of 14,327 in the U.S. and the 198th largest of 1,358 wind plants. By 2025 generation it is the 36th largest of 167 generating plants in the state.

Chevelon Butte Phase 2 within Arizona, 2025
MeasureThis plantArizonaShare
Capacity (MW)21640,5140.5%
Generation (MWh)525,472115,800,3780.5%
Wind capacity (MW)2161,20517.9%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Chevelon Butte Phase 2 plant, and when do they retire?

1 operable generator totals 216 MW, with an average age of 1 year weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1216100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
CHVB2OperatingOnshore Wind Turbine2162024n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Chevelon Butte Phase 2 plant?

EIA lists no joint owners for Chevelon Butte Phase 2. AES Clean Energy operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Chevelon Butte Phase 2 plant?

Chevelon Butte Phase 2 is in Winslow, Coconino County, Arizona, at 34.6821° N, 110.8030° W. It sits in the Arizona Public Service Company balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in Arizona are similar in size?

Arizona has 8 operable wind plants with 1,205 MW of capacity, and Chevelon Butte Phase 2's 216 MW is 18% of that.

Wind plants in Arizona around this size
PlantCountyMW2025 MWh
Mohave County Wind FarmMohave350997,150
Chevelon Butte Wind FarmCoconino238624,169
Chevelon Butte Phase 2Coconino216525,472
Babbitt Ranch Energy CenterCoconino163552,206

Source: EIA Forms EIA-860 and EIA-923, 2025.