Skip to main content
RateWatt

Natural gas power plant, Wisconsin

Custer Energy Center, Wisconsin

Custer Energy Center is a 24.5 MW natural gas power plant in Manitowoc County, Wisconsin, operated by Manitowoc Public Utilities, and it generated 4,101 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 15th percentile of U.S. natural gas plants. By 2025 generation it ranks 8,629th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

24.5 MWNameplate capacity
2%Capacity factor, 2025, 15th percentile, on 22 MW net summer
8,629thU.S. rank by generation, 2025
26 yearsAverage generator age, by MW

How hard does the Custer Energy Center plant run compared with other natural gas plants?

The Custer Energy Center plant had a capacity factor of 2% in 2025 on 22 MW of net summer capacity, the 15th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 8 days at full output out of 365.

0%Shaded: the middle half of natural gas plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Custer Energy Center2%
Natural gas plants, 75th percentile56%
Natural gas plants, median22%
Natural gas plants, 25th percentile6%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Custer Energy Center plant generating more or less than last year?

Generation at Custer Energy Center fell 26.0% from 2024 to 2025, from 5,544 MWh to 4,101 MWh.

Net generation by period
PeriodMWh
20245,544
20254,101
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 2025387
November 2025345
October 2025273
September 2025347
August 2025460
July 2025488
June 2025431
May 2025281
April 2025193
March 2025221
February 2025310
January 2025365
December 2024489
November 2024423
October 2024357
September 2024465
August 2024541
July 2024563
June 2024531
May 2024465
April 2024308
March 2024474
February 2024422
January 2024507

Source: EIA Form EIA-923, through August 2026.

How much of Wisconsin's electricity comes from the Custer Energy Center plant?

Custer Energy Center made 0.0% of the 66,249,756 MWh reported by Wisconsin plants in 2025, from 0.1% of the state's 19,442 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 78th largest of 273 plants in Wisconsin, the 4,598th largest of 14,327 in the U.S. and the 1,256th largest of 1,962 natural gas plants. By 2025 generation it is the 175th largest of 259 generating plants in the state.

Custer Energy Center within Wisconsin, 2025
MeasureThis plantWisconsinShare
Capacity (MW)2519,4420.1%
Generation (MWh)4,10166,249,7560.0%
Natural gas capacity (MW)257,8240.3%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Custer Energy Center plant, and when do they retire?

1 operable generator totals 24.5 MW, with an average age of 26 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1990s125100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingNatural Gas Fired Combustion Turbine251999n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Custer Energy Center plant?

EIA lists no joint owners for Custer Energy Center. Manitowoc Public Utilities operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Manitowoc Public Utilities charge homes?

Manitowoc Public Utilities, the operator of Custer Energy Center, had an average residential price of 11.44¢ per kWh and an average bill of $65 a month in 2025, 37% below the Wisconsin average of 18.08¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Wisconsin
Manitowoc Public Utilities11.44¢$6537% lower
Wisconsin average18.08¢$121
U.S. average17.23¢$1515% lower

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Custer Energy Center plant?

Custer Energy Center is in Manitowoc, Manitowoc County, Wisconsin, at 44.0854° N, 87.7261° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region MRO).

Source: EIA Form EIA-860, Plant, 2025 final.

Which natural gas plants in Wisconsin are similar in size?

Wisconsin has 38 operable natural gas plants with 7,824 MW of capacity, and Custer Energy Center's 24.5 MW is 0% of that.

Natural gas plants in Wisconsin around this size
PlantCountyMW2025 MWh
Consumer Operations LLCBrown48224,946
Kaukauna Paper MillOutagamie4553,758
Sycamore (WI)Dane4228
Custer Energy CenterManitowoc254,101
MMSD Jones Island WastewaterMilwaukee2264,146
Georgia-Pacific Corp - Nekoosa MillWood2275,973
Kaukauna Gas TurbineOutagamie182,340

Source: EIA Forms EIA-860 and EIA-923, 2025.