Dry Bridge Solar (Brown University) is a 40 MW solar power plant in Washington County, Rhode Island, operated by MN8 Energy LLC, and it generated 67,601 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.7% of the generation reported in Rhode Island, and its capacity factor sits at the 22nd percentile of U.S. solar plants. By 2025 generation it ranks 3,777th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

40 MWNameplate capacity
19%Capacity factor, 2025, 22nd percentile, on 40 MW net summer
0.7%Of RI generation, 2025
2 yearsAverage generator age, by MW

How hard does the Dry Bridge Solar (Brown University) plant run compared with other solar plants?

The Dry Bridge Solar (Brown University) plant had a capacity factor of 19% in 2025 on 40 MW of net summer capacity, the 22nd percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 70 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Dry Bridge Solar (Brown University)19%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Dry Bridge Solar (Brown University) plant generating more or less than last year?

Generation at Dry Bridge Solar (Brown University) rose 8.7% from 2024 to 2025, from 62,195 MWh to 67,601 MWh. Through August 2026 it is running 12.3% behind the same months of 2025.

Net generation by period
PeriodMWh
202462,195
202567,601
2026 through August43,330
2025, same months49,409
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 20266,606
July 20266,746
June 20266,572
May 20266,593
April 20266,266
March 20265,181
February 20263,758
January 20261,608
December 20252,719
November 20253,650
October 20255,510
September 20256,313
August 20258,099
July 20256,718
June 20257,312
May 20256,489
April 20256,546
March 20256,115
February 20254,389
January 20253,741
December 20242,829
November 20244,431
October 20245,695
September 20246,112
August 20246,530
July 20246,647
June 20247,862
May 20246,872
April 20245,896
March 20245,655
February 20242,494
January 20241,172

Source: EIA Form EIA-923, through August 2026.

How much of Rhode Island's electricity comes from the Dry Bridge Solar (Brown University) plant?

Dry Bridge Solar (Brown University) made 0.7% of the 9,791,976 MWh reported by Rhode Island plants in 2025, from 1.6% of the state's 2,577 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 7th largest of 112 plants in Rhode Island, the 4,074th largest of 14,327 in the U.S. and the 969th largest of 7,223 solar plants. By 2025 generation it is the 10th largest of 106 generating plants in the state.

Dry Bridge Solar (Brown University) within Rhode Island, 2025
MeasureThis plantRhode IslandShare
Capacity (MW)402,5771.6%
Generation (MWh)67,6019,791,9760.7%
Solar capacity (MW)404528.9%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Dry Bridge Solar (Brown University) plant, and when do they retire?

4 operable generators total 40 MW, with an average age of 2 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s440100%none reported
Every generator, 4 in all
UnitStatusTechnologyMWIn servicePlanned retirement
DBS1OperatingSolar Photovoltaic102023n/a
DBS2OperatingSolar Photovoltaic102023n/a
DBS3OperatingSolar Photovoltaic102023n/a
DBS4OperatingSolar Photovoltaic102023n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Dry Bridge Solar (Brown University) plant?

Dry Bridge Solar 1, LLC is the only joint owner reported for Dry Bridge Solar (Brown University), with 100.0%. MN8 Energy LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Dry Bridge Solar (Brown University) plant?

Dry Bridge Solar (Brown University) is in North Kingstown, Washington County, Rhode Island, at 41.5574° N, 71.5073° W. It sits in the ISO New England Inc. balancing area (NERC region NPCC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Rhode Island are similar in size?

Rhode Island has 77 operable solar plants with 452 MW of capacity, and Dry Bridge Solar (Brown University)'s 40 MW is 9% of that.

Solar plants in Rhode Island around this size
PlantCountyMW2025 MWh
Robin Hollow SolarKent4167,931
Dry Bridge Solar (Brown University)Washington4067,601
University Solar, LLCKent2428,457
GD West Greenwich Nooseneck I, LLCKent2031,092