El Cajon Energy Center is a 60.5 MW natural gas power plant in San Diego County, California, operated by Wellhead Services, Inc, and it generated 19,841 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 20th percentile of U.S. natural gas plants. By 2025 generation it ranks 5,269th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the El Cajon Energy Center plant run compared with other natural gas plants?
The El Cajon Energy Center plant had a capacity factor of 4% in 2025 on 60.5 MW of net summer capacity, the 20th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 14 days at full output out of 365.
0%Shaded: the middle half of natural gas plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| El Cajon Energy Center | 4% |
| Natural gas plants, 75th percentile | 56% |
| Natural gas plants, median | 22% |
| Natural gas plants, 25th percentile | 6% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the El Cajon Energy Center plant generating more or less than last year?
El Cajon Energy Center generated 19,841 MWh in 2025; EIA reports no 2024 total to compare. 2024 has output for only 11 months, so the two years are not compared.
| Period | MWh |
|---|---|
| 2024 | 8,981 |
| 2025 | 19,841 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 6,055 |
| November 2025 | 2,094 |
| October 2025 | 767 |
| September 2025 | 7,516 |
| August 2025 | 1,708 |
| July 2025 | 219 |
| June 2025 | 484 |
| May 2025 | 194 |
| April 2025 | 70 |
| March 2025 | 0 |
| February 2025 | 122 |
| January 2025 | 611 |
| December 2024 | 59 |
| November 2024 | 0 |
| October 2024 | 1,178 |
| September 2024 | 2,937 |
| August 2024 | 2,064 |
| July 2024 | 1,474 |
| June 2024 | 546 |
| May 2024 | 42 |
| April 2024 | 201 |
| March 2024 | 41 |
| February 2024 | 70 |
| January 2024 | 371 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the El Cajon Energy Center plant, and when do they retire?
1 operable generator totals 60.5 MW, with an average age of 15 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 61 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GEN1 | Operating | Natural Gas Fired Combustion Turbine | 61 | 2010 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the El Cajon Energy Center plant?
EIA lists no joint owners for El Cajon Energy Center. Wellhead Services, Inc operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the El Cajon Energy Center plant?
El Cajon Energy Center is in El Cajon, San Diego County, California, at 32.7961° N, 116.9721° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which natural gas plants in California are similar in size?
California has 304 operable natural gas plants with 40,211 MW of capacity, and El Cajon Energy Center's 60.5 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| CalPeak Power Panoche Peaker Plant | Fresno | 61 | 1,871 |
| Border Hybrid Energy Center | San Diego | 61 | 9,104 |
| Agua Mansa Power Plant | San Bernardino | 61 | 3,753 |
| El Cajon Energy Center | San Diego | 61 | 19,841 |
| Delano Energy Center | Tulare | 61 | 2,394 |
| CalPeak Power Enterprise Peaker Plant | San Diego | 59 | 2,206 |
| Ellwood | Santa Barbara | 58 | 305 |