Solar power plant, Pennsylvania
Gaucho Solar power plant, Pennsylvania
Gaucho Solar is a 20 MW solar power plant in Beaver County, Pennsylvania, operated by Gaucho Solar, and it generated 31,966 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 18th percentile of U.S. solar plants. By 2025 generation it ranks 4,664th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Gaucho Solar plant run compared with other solar plants?
The Gaucho Solar plant had a capacity factor of 18% in 2025 on 20 MW of net summer capacity, the 18th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 67 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Gaucho Solar | 18% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Gaucho Solar plant generating more or less than last year?
Generation at Gaucho Solar fell 5.9% from 2024 to 2025, from 33,958 MWh to 31,966 MWh.
| Period | MWh |
|---|---|
| 2024 | 33,958 |
| 2025 | 31,966 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 711 |
| November 2025 | 1,444 |
| October 2025 | 2,827 |
| September 2025 | 3,360 |
| August 2025 | 4,091 |
| July 2025 | 4,079 |
| June 2025 | 3,729 |
| May 2025 | 3,159 |
| April 2025 | 3,171 |
| March 2025 | 2,857 |
| February 2025 | 1,521 |
| January 2025 | 1,017 |
| December 2024 | 1,178 |
| November 2024 | 1,508 |
| October 2024 | 3,221 |
| September 2024 | 3,295 |
| August 2024 | 3,679 |
| July 2024 | 4,210 |
| June 2024 | 3,910 |
| May 2024 | 3,806 |
| April 2024 | 2,960 |
| March 2024 | 2,851 |
| February 2024 | 2,497 |
| January 2024 | 843 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Gaucho Solar plant, and when do they retire?
1 operable generator totals 20 MW, with an average age of 2 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 20 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GCHOS | Operating | Solar Photovoltaic | 20 | 2023 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Gaucho Solar plant?
EIA lists no joint owners for Gaucho Solar. Gaucho Solar operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Gaucho Solar plant?
Gaucho Solar is in Clinton, Beaver County, Pennsylvania, at 40.5116° N, 80.3134° W. It sits in the PJM Interconnection, LLC balancing area (NERC region RFC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Pennsylvania are similar in size?
Pennsylvania has 74 operable solar plants with 1,131 MW of capacity, and Gaucho Solar's 20 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Cottontail Solar 5 | Juniata | 20 | 32,025 |
| Cottontail Solar 6 | Snyder | 20 | 37,921 |
| Cottontail Solar 8 | York | 20 | 35,800 |
| Gaucho Solar | Beaver | 20 | 31,966 |
| Lyons Solar | Berks | 20 | 34,933 |
| Cobalt Solar, LLC | Forest | 20 | 18,905 |
| Erie Solar, LLC | Erie | 20 | 23,277 |
Source: EIA Forms EIA-860 and EIA-923, 2025.