Solar power plant, Idaho
Grand View Solar Two power plant, Idaho
Grand View Solar Two is a 80 MW solar power plant in Elmore County, Idaho, operated by Grand View PV Solar Two, LLC, and it generated 183,722 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.9% of the generation reported in Idaho, and its capacity factor sits at the 72nd percentile of U.S. solar plants. By 2025 generation it ranks 2,611th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Grand View Solar Two plant run compared with other solar plants?
The Grand View Solar Two plant had a capacity factor of 26% in 2025 on 80 MW of net summer capacity, the 72nd percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 96 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Grand View Solar Two | 26% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Grand View Solar Two plant generating more or less than last year?
Generation at Grand View Solar Two rose 3.4% from 2024 to 2025, from 177,622 MWh to 183,722 MWh. Through August 2026 it is running 8.4% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 177,622 |
| 2025 | 183,722 |
| 2026 through August | 129,567 |
| 2025, same months | 141,431 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 17,797 |
| July 2026 | 20,116 |
| June 2026 | 22,048 |
| May 2026 | 23,293 |
| April 2026 | 18,367 |
| March 2026 | 14,698 |
| February 2026 | 8,196 |
| January 2026 | 5,052 |
| December 2025 | 5,561 |
| November 2025 | 7,535 |
| October 2025 | 12,572 |
| September 2025 | 16,623 |
| August 2025 | 20,936 |
| July 2025 | 23,816 |
| June 2025 | 24,442 |
| May 2025 | 22,988 |
| April 2025 | 18,040 |
| March 2025 | 14,142 |
| February 2025 | 8,909 |
| January 2025 | 8,158 |
| December 2024 | 4,791 |
| November 2024 | 7,038 |
| October 2024 | 13,626 |
| September 2024 | 17,273 |
| August 2024 | 21,111 |
| July 2024 | 22,857 |
| June 2024 | 24,129 |
| May 2024 | 21,927 |
| April 2024 | 16,888 |
| March 2024 | 14,185 |
| February 2024 | 8,138 |
| January 2024 | 5,659 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Grand View Solar Two plant, and when do they retire?
2 operable generators total 80 MW, with an average age of 9 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 2 | 80 | 100% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GVS2 | Operating | Solar Photovoltaic | 60 | 2016 | n/a |
| GVS5 | Operating | Solar Photovoltaic | 20 | 2016 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Grand View Solar Two plant?
EIA lists no joint owners for Grand View Solar Two. Grand View PV Solar Two, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Grand View Solar Two plant?
Grand View Solar Two is in Grand View, Elmore County, Idaho, at 42.9896° N, 116.0934° W. It sits in the Idaho Power Company balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Idaho are similar in size?
Idaho has 13 operable solar plants with 702 MW of capacity, and Grand View Solar Two's 80 MW is 11% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Jackpot Solar, LLC | Twin Falls | 120 | 274,519 |
| Franklin Solar Hybrid | Twin Falls | 100 | 252,389 |
| Grand View Solar Two | Elmore | 80 | 183,722 |
| ID Solar | Ada | 40 | 92,218 |
| Black Mesa Solar, LLC | Elmore | 40 | 89,175 |
Source: EIA Forms EIA-860 and EIA-923, 2025.