Solar power plant, Texas

Greasewood II LLC solar power plant, Texas

Greasewood II LLC is a 306 MW solar power plant in Pecos County, Texas, operated by Greasewood II LLC, and it generated 796,894 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Texas, and its capacity factor sits at the 89th percentile of U.S. solar plants. By 2025 generation it ranks 882nd of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

306 MWNameplate capacity
30%Capacity factor, 2025, 89th percentile, on 306 MW net summer
0.1%Of TX generation, 2025
1 yearAverage generator age, by MW

How hard does the Greasewood II LLC plant run compared with other solar plants?

The Greasewood II LLC plant had a capacity factor of 30% in 2025 on 306 MW of net summer capacity, the 89th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 109 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Greasewood II LLC30%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Greasewood II LLC plant generating more or less than last year?

Greasewood II LLC generated 796,894 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 7.7% ahead of the same months of 2025. 2024 has output for only 3 months, so the two years are not compared.

Net generation by period
PeriodMWh
2024178,438
2025796,894
2026 through August593,708
2025, same months551,357
Monthly generation, Oct 2024 to Aug 2026
MonthMWh
August 202689,531
July 202682,363
June 202678,615
May 202678,872
April 202671,672
March 202681,090
February 202660,515
January 202651,050
December 202550,626
November 202557,969
October 202569,104
September 202567,838
August 202583,453
July 202589,469
June 202584,934
May 202585,234
April 202575,932
March 202569,938
February 202523,418
January 202538,979
December 202450,442
November 202454,109
October 202473,887

Source: EIA Form EIA-923, through August 2026.

How much of Texas' electricity comes from the Greasewood II LLC plant?

Greasewood II LLC made 0.1% of the 592,896,176 MWh reported by Texas plants in 2025, from 0.2% of the state's 195,966 MW of capacity. By capacity it is the 156th largest of 1,023 plants in Texas, the 1,016th largest of 14,327 in the U.S. and the 38th largest of 7,223 solar plants. By 2025 generation it is the 157th largest of 816 generating plants in the state.

Greasewood II LLC within Texas, 2025
MeasureThis plantTexasShare
Capacity (MW)306195,9660.2%
Generation (MWh)796,894592,896,1760.1%
Solar capacity (MW)30630,7391.0%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Greasewood II LLC plant, and when do they retire?

1 operable generator totals 306 MW, with an average age of 1 year weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1306100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
TBSPOperatingSolar Photovoltaic3062024n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Greasewood II LLC plant?

EIA lists no joint owners for Greasewood II LLC. Greasewood II LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Greasewood II LLC plant?

Greasewood II LLC is in Girvin, Pecos County, Texas, at 31.1041° N, 102.6063° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Texas are similar in size?

Texas has 225 operable solar plants with 30,739 MW of capacity, and Greasewood II LLC's 306 MW is 1% of that.

Solar plants in Texas around this size
PlantCountyMW2025 MWh
IP Radian, LLCBrown320657,714
Delilah Solar Energy II LLCRed River310558,764
BT Hickerson Solar, LLCBosque310205,489
Greasewood II LLCPecos306796,894
Juno Solar ProjectBorden306766,600
Prospero SolarAndrews300759,356
Delilah Solar Energy LLCRed River300557,763

Source: EIA Forms EIA-860 and EIA-923, 2025.