Natural gas power plant, California
Greenleaf 2 Power Plant, California
Greenleaf 2 Power Plant is a 49.5 MW natural gas power plant in Sutter County, California, operated by Greenleaf Energy LLC, and it generated 36,783 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 33rd percentile of U.S. natural gas plants. By 2025 generation it ranks 4,477th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does Greenleaf 2 Power Plant run compared with other natural gas plants?
Greenleaf 2 Power Plant had a capacity factor of 8% in 2025 on 49.5 MW of net summer capacity, the 33rd percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 31 days at full output out of 365.
0%Shaded: the middle half of natural gas plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Greenleaf 2 Power Plant | 8% |
| Natural gas plants, 75th percentile | 56% |
| Natural gas plants, median | 22% |
| Natural gas plants, 25th percentile | 6% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is Greenleaf 2 Power Plant generating more or less than last year?
Greenleaf 2 Power Plant generated 36,783 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 483.0% ahead of the same months of 2025. 2024 has output for only 10 months, so the two years are not compared.
| Period | MWh |
|---|---|
| 2024 | 30,458 |
| 2025 | 36,783 |
| 2026 through August | 31,368 |
| 2025, same months | 5,380 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 0 |
| July 2026 | 0 |
| June 2026 | 431 |
| May 2026 | 1,978 |
| April 2026 | 10,862 |
| March 2026 | 15,966 |
| February 2026 | 1,963 |
| January 2026 | 168 |
| December 2025 | 14,335 |
| November 2025 | 15,040 |
| October 2025 | 1,537 |
| September 2025 | 491 |
| August 2025 | 982 |
| July 2025 | 0 |
| June 2025 | 457 |
| May 2025 | 0 |
| April 2025 | 200 |
| March 2025 | 3,741 |
| February 2025 | 0 |
| January 2025 | 0 |
| December 2024 | 2,434 |
| November 2024 | 3,764 |
| October 2024 | 967 |
| September 2024 | 3,268 |
| August 2024 | 4,071 |
| July 2024 | 8,353 |
| June 2024 | 3,701 |
| May 2024 | 770 |
| April 2024 | 1,992 |
| March 2024 | 1,138 |
| February 2024 | 0 |
| January 2024 | 0 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at Greenleaf 2 Power Plant, and when do they retire?
1 operable generator totals 49.5 MW, with an average age of 36 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1980s | 1 | 50 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GEN1 | Operating | Natural Gas Fired Combustion Turbine | 50 | 1989 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns Greenleaf 2 Power Plant?
EIA lists no joint owners for Greenleaf 2 Power Plant. Greenleaf Energy LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is Greenleaf 2 Power Plant?
Greenleaf 2 Power Plant is in Yuba City, Sutter County, California, at 39.1365° N, 121.6397° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which natural gas plants in California are similar in size?
California has 304 operable natural gas plants with 40,211 MW of capacity, and Greenleaf 2 Power Plant's 49.5 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Barre Peaker | Orange | 50 | 5,447 |
| Center Hybrid | Los Angeles | 50 | 1,974 |
| Chowchilla II | Madera | 50 | 13,727 |
| Greenleaf 2 Power Plant | Sutter | 50 | 36,783 |
| AltaGas Ripon Energy Inc. | San Joaquin | 50 | 920 |
| Santa Ynez Facility | Santa Barbara | 49 | n/a |
| Clearwater Power Plant | Riverside | 49 | 3,539 |
Source: EIA Forms EIA-860 and EIA-923, 2025.