Skip to main content
RateWatt

Solar power plant, California

Imperial Solar Energy Center South power plant, California

Imperial Solar Energy Center South is a 129 MW solar power plant in Imperial County, California, operated by CSOLAR IV South LLC, and it generated 251,092 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in California, and its capacity factor sits at the 43rd percentile of U.S. solar plants. By 2025 generation it ranks 2,226th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

129 MWNameplate capacity
22%Capacity factor, 2025, 43rd percentile, on 129 MW net summer
0.1%Of CA generation, 2025
12 yearsAverage generator age, by MW

How hard does the Imperial Solar Energy Center South plant run compared with other solar plants?

The Imperial Solar Energy Center South plant had a capacity factor of 22% in 2025 on 129 MW of net summer capacity, the 43rd percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 81 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Imperial Solar Energy Center South22%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Imperial Solar Energy Center South plant generating more or less than last year?

Generation at Imperial Solar Energy Center South fell 5.0% from 2024 to 2025, from 264,268 MWh to 251,092 MWh.

Net generation by period
PeriodMWh
2024264,268
2025251,092
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 202517,489
November 202517,772
October 202523,428
September 202521,718
August 202522,262
July 202524,606
June 202523,923
May 202523,559
April 202521,537
March 202518,004
February 202517,612
January 202519,182
December 202418,329
November 202420,431
October 202423,296
September 202425,657
August 202425,611
July 202423,696
June 202424,700
May 202423,498
April 202420,273
March 202421,009
February 202419,545
January 202418,223

Source: EIA Form EIA-923, through August 2026.

How much of California's electricity comes from the Imperial Solar Energy Center South plant?

Imperial Solar Energy Center South made 0.1% of the 204,542,898 MWh reported by California plants in 2025, from 0.1% of the state's 107,433 MW of capacity. By capacity it is the 219th largest of 1,877 plants in California, the 2,233rd largest of 14,327 in the U.S. and the 357th largest of 7,223 solar plants. By 2025 generation it is the 218th largest of 1,608 generating plants in the state.

Imperial Solar Energy Center South within California, 2025
MeasureThis plantCaliforniaShare
Capacity (MW)129107,4330.1%
Generation (MWh)251,092204,542,8980.1%
Solar capacity (MW)12924,6630.5%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Imperial Solar Energy Center South plant, and when do they retire?

1 operable generator totals 129 MW, with an average age of 12 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s1129100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
56819OperatingSolar Photovoltaic1292013n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Imperial Solar Energy Center South plant?

3 owners report shares in Imperial Solar Energy Center South; Tenaska CSOLAR South Holdings, LLC holds the largest named share, 49.0% or about 63.2 MW. CSOLAR IV South LLC operates the plant.

Reported ownership of operable capacity
OwnerShareMW2025 MWh, by share
Tenaska CSOLAR South Holdings, LLC49.0%63123,035
Tenaska IV South Partners, LLC48.0%62120,524
Tenaska CSOLAR South, LLC3.0%47,533

Source: EIA Form EIA-860, Owner, 2025 final. MW and MWh by share multiply the plant totals by each owner's percentage.

Where is the Imperial Solar Energy Center South plant?

Imperial Solar Energy Center South is in Calexico, Imperial County, California, at 32.6633° N, 115.6583° W. It sits in the California Independent System Operator balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in California are similar in size?

California has 934 operable solar plants with 24,663 MW of capacity, and Imperial Solar Energy Center South's 129 MW is 1% of that.

Solar plants in California around this size
PlantCountyMW2025 MWh
Blythe Solar II, LLCRiverside131351,256
Arlington Energy Center IIIRiverside131340,489
CA Flats Solar 130, LLCSan Luis Obispo130261,824
Imperial Solar Energy Center SouthImperial129251,092
American Kings Solar, LLCKings128324,421
BigBeau Solar, LLCKern128365,205
Ivanpah 1San Bernardino126200,392

Source: EIA Forms EIA-860 and EIA-923, 2025.