Wind power plant, Texas
Inadale Wind Farm LLC Hybrid power plant, Texas
Inadale Wind Farm LLC Hybrid is a 207 MW power plant, 197 MW of it wind, in Nolan County, Texas, operated by RWE Clean Energy, and it generated 321,174 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Texas, and its capacity factor sits at the 8th percentile of U.S. wind plants. By 2025 generation it ranks 1,877th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Inadale Wind Farm LLC Hybrid plant run compared with other wind plants?
The Inadale Wind Farm LLC Hybrid plant's wind units had a capacity factor of 19% in 2025 on 197 MW of net summer capacity, the 8th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 68 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Inadale Wind Farm LLC Hybrid | 19% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its wind generators only. Values above 105% are left out of the comparison.
Is the Inadale Wind Farm LLC Hybrid plant generating more or less than last year?
Generation at Inadale Wind Farm LLC Hybrid fell 4.1% from 2024 to 2025, from 335,063 MWh to 321,174 MWh.
| Period | MWh |
|---|---|
| 2024 | 335,063 |
| 2025 | 321,174 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 33,012 |
| November 2025 | 17,751 |
| October 2025 | 18,031 |
| September 2025 | 19,102 |
| August 2025 | 22,834 |
| July 2025 | 28,681 |
| June 2025 | 47,243 |
| May 2025 | 32,292 |
| April 2025 | 32,024 |
| March 2025 | 24,622 |
| February 2025 | 24,708 |
| January 2025 | 20,874 |
| December 2024 | 26,104 |
| November 2024 | 21,994 |
| October 2024 | 20,093 |
| September 2024 | 19,081 |
| August 2024 | 28,509 |
| July 2024 | 30,730 |
| June 2024 | 42,280 |
| May 2024 | 31,906 |
| April 2024 | 27,945 |
| March 2024 | 23,685 |
| February 2024 | 32,885 |
| January 2024 | 29,851 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Inadale Wind Farm LLC Hybrid plant, and when do they retire?
2 operable generators total 207 MW, with an average age of 16 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2000s | 1 | 197 | 95% | none reported |
| 2010s | 1 | 10 | 5% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Onshore Wind Turbine | 197 | 2009 | n/a |
| INABT | Operating | Batteries | 10 | 2018 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Inadale Wind Farm LLC Hybrid plant?
EIA lists no joint owners for Inadale Wind Farm LLC Hybrid. RWE Clean Energy operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What fuels does the Inadale Wind Farm LLC Hybrid plant use?
Inadale Wind Farm LLC Hybrid has capacity on 2 fuels: 95% wind and 5% battery and pumped storage. In 2025, wind made 100% of its output.
| Fuel | MW | Share | 2025 MWh |
|---|---|---|---|
| Wind | 197 | 95.2% | 322,030 |
| Battery and pumped storage | 10 | 4.8% | -856 |
Source: EIA Forms EIA-860 and EIA-923, 2025.
Where is the Inadale Wind Farm LLC Hybrid plant?
Inadale Wind Farm LLC Hybrid is in Roscoe, Nolan County, Texas, at 32.4969° N, 100.5797° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Texas are similar in size?
Texas has 228 operable wind plants with 43,942 MW of capacity, and Inadale Wind Farm LLC Hybrid's 197 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Live Oak Wind Project | Schleicher | 200 | 791,664 |
| La Chalupa, LLC | Cameron | 199 | 443,574 |
| Trinity Hills | Young | 198 | 767,441 |
| Inadale Wind Farm LLC Hybrid | Nolan | 197 | 322,030 |
| Castle Gap Wind | Mills | 197 | 632,524 |
| Bearkat | Glasscock | 197 | 648,295 |
| Spinning Spur Wind III | Oldham | 194 | 718,566 |
Source: EIA Forms EIA-860 and EIA-923, 2025.