Skip to main content
RateWatt

Wind power plant, Texas

Trinity Hills wind power plant, Texas

Trinity Hills is a 198 MW wind power plant in Young County, Texas, operated by Trinity Hills Wind Farm LLC, and it generated 767,441 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Texas, and its capacity factor sits at the 88th percentile of U.S. wind plants. By 2025 generation it ranks 915th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

198 MWNameplate capacity
44%Capacity factor, 2025, 88th percentile, on 198 MW net summer
0.1%Of TX generation, 2025
14 yearsAverage generator age, by MW

How hard does the Trinity Hills plant run compared with other wind plants?

The Trinity Hills plant had a capacity factor of 44% in 2025 on 198 MW of net summer capacity, the 88th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 161 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Trinity Hills44%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Trinity Hills plant generating more or less than last year?

Generation at Trinity Hills rose 1.9% from 2024 to 2025, from 752,898 MWh to 767,441 MWh. Through August 2026 it is running 9.9% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024752,898
2025767,441
2026 through August557,036
2025, same months506,774
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202654,538
July 202650,397
June 202674,953
May 202665,303
April 202687,455
March 202691,627
February 202660,817
January 202671,946
December 202577,387
November 202567,557
October 202566,596
September 202549,127
August 202546,194
July 202559,557
June 202566,038
May 202552,548
April 202578,617
March 202584,982
February 202556,454
January 202562,384
December 202459,285
November 202462,570
October 202470,189
September 202435,925
August 202457,380
July 202456,412
June 202458,427
May 202464,199
April 202480,576
March 202477,111
February 202476,680
January 202454,144

Source: EIA Form EIA-923, through August 2026.

How much of Texas' electricity comes from the Trinity Hills plant?

Trinity Hills made 0.1% of the 592,896,176 MWh reported by Texas plants in 2025, from 0.1% of the state's 195,966 MW of capacity. Its share of output is 1.3 times its share of capacity. By capacity it is the 337th largest of 1,023 plants in Texas, the 1,663rd largest of 14,327 in the U.S. and the 340th largest of 1,358 wind plants. By 2025 generation it is the 163rd largest of 816 generating plants in the state.

Trinity Hills within Texas, 2025
MeasureThis plantTexasShare
Capacity (MW)198195,9660.1%
Generation (MWh)767,441592,896,1760.1%
Wind capacity (MW)19843,9420.5%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Trinity Hills plant, and when do they retire?

1 operable generator totals 198 MW, with an average age of 14 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s1198100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingOnshore Wind Turbine1982011n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Trinity Hills plant?

2 owners report shares in Trinity Hills; Texas Wind Repower HoldCo, L.P. c/o Concord Infrastructure Investments, LLC holds the largest named share, 66.6% or about 132 MW. Trinity Hills Wind Farm LLC operates the plant.

Reported ownership of operable capacity
OwnerShareMW2025 MWh, by share
Texas Wind Repower HoldCo, L.P. c/o Concord Infrastructure Investments, LLC66.6%132511,116
UBS Asset Management (Americas) Inc33.4%66256,325

Source: EIA Form EIA-860, Owner, 2025 final. MW and MWh by share multiply the plant totals by each owner's percentage.

Where is the Trinity Hills plant?

Trinity Hills is in Olney, Young County, Texas, at 33.3836° N, 98.7119° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in Texas are similar in size?

Texas has 228 operable wind plants with 43,942 MW of capacity, and Trinity Hills' 198 MW is 0% of that.

Wind plants in Texas around this size
PlantCountyMW2025 MWh
Flat Top Wind IMills200786,606
Live Oak Wind ProjectSchleicher200791,664
La Chalupa, LLCCameron199443,574
Trinity HillsYoung198767,441
Inadale Wind Farm LLC HybridNolan197322,030
Castle Gap WindMills197632,524
BearkatGlasscock197648,295

Source: EIA Forms EIA-860 and EIA-923, 2025.