Jim Bridger is a 2,326 MW power plant, 1,164 MW of it natural gas, in Sweetwater County, Wyoming, operated by PacifiCorp, and it generated 7,596,779 MWh in 2025 (Forms EIA-860 and EIA-923). That is 16.7% of the generation reported in Wyoming, and its capacity factor sits at the 57th percentile of U.S. natural gas plants. By 2025 generation it ranks 113th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Jim Bridger plant run compared with other natural gas plants?
The Jim Bridger plant's natural gas units had a capacity factor of 29% in 2025 on 1,070 MW of net summer capacity, the 57th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 106 days at full output out of 365.
0%Shaded: the middle half of natural gas plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Jim Bridger | 29% |
| Natural gas plants, 75th percentile | 56% |
| Natural gas plants, median | 22% |
| Natural gas plants, 25th percentile | 6% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its natural gas generators only. Values above 105% are left out of the comparison.
Is the Jim Bridger plant generating more or less than last year?
Generation at Jim Bridger fell 2.7% from 2024 to 2025, from 7,806,785 MWh to 7,596,779 MWh. Through August 2026 it is running 6.9% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 7,806,785 |
| 2025 | 7,596,779 |
| 2026 through August | 4,630,517 |
| 2025, same months | 4,974,878 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 1,098,147 |
| July 2026 | 1,114,488 |
| June 2026 | 540,442 |
| May 2026 | 449,917 |
| April 2026 | 275,821 |
| March 2026 | 300,246 |
| February 2026 | 339,218 |
| January 2026 | 512,238 |
| December 2025 | 472,271 |
| November 2025 | 815,372 |
| October 2025 | 654,435 |
| September 2025 | 679,823 |
| August 2025 | 920,226 |
| July 2025 | 968,429 |
| June 2025 | 712,964 |
| May 2025 | 382,745 |
| April 2025 | 360,201 |
| March 2025 | 440,436 |
| February 2025 | 468,541 |
| January 2025 | 721,336 |
| December 2024 | 904,854 |
| November 2024 | 678,732 |
| October 2024 | 758,658 |
| September 2024 | 773,287 |
| August 2024 | 889,889 |
| July 2024 | 978,585 |
| June 2024 | 568,523 |
| May 2024 | 328,564 |
| April 2024 | 373,320 |
| March 2024 | 374,596 |
| February 2024 | 533,497 |
| January 2024 | 644,280 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Jim Bridger plant, and when do they retire?
4 operable generators total 2,326 MW, with an average age of 49 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1970s | 4 | 2,326 | 100% | none reported |
Every generator, 4 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Natural Gas Steam Turbine | 578 | 1974 | n/a |
| 2 | Operating | Natural Gas Steam Turbine | 586 | 1975 | n/a |
| 3 | Operating | Conventional Steam Coal | 578 | 1976 | n/a |
| 4 | Operating | Conventional Steam Coal | 584 | 1979 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Jim Bridger plant?
2 owners report shares in Jim Bridger; PacifiCorp holds the largest named share, 66.7% or about 1,551 MW. PacifiCorp operates the plant.
| Owner | Share | MW | 2025 MWh, by share |
|---|---|---|---|
| PacifiCorp | 66.7% | 1,551 | 5,064,773 |
| Idaho Power Co | 33.3% | 775 | 2,532,006 |
Source: EIA Form EIA-860, Owner, 2025 final. MW and MWh by share multiply the plant totals by each owner's percentage.
What does PacifiCorp charge homes?
PacifiCorp, the operator of Jim Bridger, had an average residential price of 15.13¢ per kWh and an average bill of $107 a month in 2025, 13% above the Wyoming average of 13.37¢.
| Measure | Price | Monthly bill | Against Wyoming |
|---|---|---|---|
| PacifiCorp | 15.13¢ | $107 | 13% higher |
| Wyoming average | 13.37¢ | $112 | |
| U.S. average | 17.23¢ | $151 | 29% higher |
Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.
What fuels does the Jim Bridger plant use?
Jim Bridger has capacity on 2 fuels: 50% natural gas and 50% coal. In 2025, natural gas made 36% of its output.
| Fuel | MW | Share | 2025 MWh |
|---|---|---|---|
| Natural gas | 1,164 | 50.0% | 2,710,516 |
| Coal | 1,162 | 50.0% | 4,876,096 |
Source: EIA Forms EIA-860 and EIA-923, 2025.
Where is the Jim Bridger plant?
Jim Bridger is in Point of Rocks, Sweetwater County, Wyoming, at 41.7378° N, 108.7875° W. It sits in the PacifiCorp - East balancing area (NERC region WECC).