Skip to main content
RateWatt

Natural gas power plant, North Carolina

Lee Combined Cycle Plant, North Carolina

Lee Combined Cycle Plant is a 1,068 MW natural gas power plant in Wayne County, North Carolina, operated by Duke Energy Progress-(NC), and it generated 5,735,818 MWh in 2025 (Forms EIA-860 and EIA-923). That is 4.3% of the generation reported in North Carolina, and its capacity factor sits at the 89th percentile of U.S. natural gas plants. By 2025 generation it ranks 189th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

1,068 MWNameplate capacity
74%Capacity factor, 2025, 89th percentile, on 888 MW net summer
4.3%Of NC generation, 2025
13 yearsAverage generator age, by MW

How hard does Lee Combined Cycle Plant run compared with other natural gas plants?

Lee Combined Cycle Plant had a capacity factor of 74% in 2025 on 888 MW of net summer capacity, the 89th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 269 days at full output out of 365.

0%Shaded: the middle half of natural gas plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Lee Combined Cycle Plant74%
Natural gas plants, 75th percentile56%
Natural gas plants, median22%
Natural gas plants, 25th percentile6%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is Lee Combined Cycle Plant generating more or less than last year?

Generation at Lee Combined Cycle Plant fell 12.4% from 2024 to 2025, from 6,549,447 MWh to 5,735,818 MWh. Through August 2026 it is running 0.9% behind the same months of 2025.

Net generation by period
PeriodMWh
20246,549,447
20255,735,818
2026 through August4,246,784
2025, same months4,287,494
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 2026622,001
July 2026615,925
June 2026362,560
May 2026170,349
April 2026623,063
March 2026658,508
February 2026579,332
January 2026615,046
December 2025621,260
November 2025366,267
October 202546,467
September 2025414,330
August 2025572,398
July 2025639,397
June 2025585,469
May 2025501,950
April 2025223,053
March 2025652,826
February 2025485,385
January 2025627,016
December 2024574,122
November 2024566,871
October 2024613,855
September 2024558,502
August 2024624,378
July 2024649,088
June 2024581,482
May 2024505,713
April 2024533,936
March 2024210,818
February 2024593,681
January 2024537,001

Source: EIA Form EIA-923, through August 2026.

How much of North Carolina's electricity comes from Lee Combined Cycle Plant?

Lee Combined Cycle Plant made 4.3% of the 134,194,434 MWh reported by North Carolina plants in 2025, from 2.7% of the state's 39,933 MW of capacity. Its share of output is 1.6 times its share of capacity. By capacity it is the 10th largest of 928 plants in North Carolina, the 285th largest of 14,327 in the U.S. and the 134th largest of 1,962 natural gas plants. By 2025 generation it is the 9th largest of 872 generating plants in the state.

Lee Combined Cycle Plant within North Carolina, 2025
MeasureThis plantNorth CarolinaShare
Capacity (MW)1,06839,9332.7%
Generation (MWh)5,735,818134,194,4344.3%
Natural gas capacity (MW)1,06818,2695.8%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at Lee Combined Cycle Plant, and when do they retire?

4 operable generators total 1,068 MW, with an average age of 13 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s41,068100%none reported
Every generator, 4 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1AOperatingNatural Gas Fired Combined Cycle2212012n/a
1BOperatingNatural Gas Fired Combined Cycle2212012n/a
1COperatingNatural Gas Fired Combined Cycle2212012n/a
ST1OperatingNatural Gas Fired Combined Cycle4052012n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns Lee Combined Cycle Plant?

EIA lists no joint owners for Lee Combined Cycle Plant. Duke Energy Progress-(NC) operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Duke Energy Progress charge homes?

Duke Energy Progress, the operator of Lee Combined Cycle Plant, had an average residential price of 15.19¢ per kWh and an average bill of $159 a month in 2025, 9% above the North Carolina average of 14.00¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst North Carolina
Duke Energy Progress15.19¢$1599% higher
North Carolina average14.00¢$146
U.S. average17.23¢$15123% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is Lee Combined Cycle Plant?

Lee Combined Cycle Plant is in Goldsboro, Wayne County, North Carolina, at 35.3736° N, 78.0894° W. It sits in the Duke Energy Carolinas balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which natural gas plants in North Carolina are similar in size?

North Carolina has 21 operable natural gas plants with 18,269 MW of capacity, and Lee Combined Cycle Plant's 1,068 MW is 6% of that.

Natural gas plants in North Carolina around this size
PlantCountyMW2025 MWh
James E. Rogers Energy ComplexCleveland1,5313,105,686
RowanRowan1,1924,272,488
Lee Combined Cycle PlantWayne1,0685,735,818
AshevilleBuncombe1,0123,653,058
Wayne County Energy ComplexWayne980559,320
Rockingham County CT StationRockingham9781,798,021

Source: EIA Forms EIA-860 and EIA-923, 2025.