Hydro power plant, Texas
Marble Falls hydroelectric power plant, Texas
Marble Falls is a 39.6 MW hydro power plant in Burnet County, Texas, operated by Lower Colorado River Authority, and it generated 23,788 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 4th percentile of U.S. hydro plants. By 2025 generation it ranks 5,024th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Marble Falls plant run compared with other hydro plants?
The Marble Falls plant had a capacity factor of 7% in 2025 on 39.6 MW of net summer capacity, the 4th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 25 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Marble Falls | 7% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Marble Falls plant generating more or less than last year?
Generation at Marble Falls rose 56.2% from 2024 to 2025, from 15,233 MWh to 23,788 MWh.
| Period | MWh |
|---|---|
| 2024 | 15,233 |
| 2025 | 23,788 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 1,238 |
| November 2025 | 772 |
| October 2025 | 199 |
| September 2025 | 986 |
| August 2025 | 1,701 |
| July 2025 | 9,803 |
| June 2025 | 2,435 |
| May 2025 | 2,873 |
| April 2025 | 1,137 |
| March 2025 | 962 |
| February 2025 | 726 |
| January 2025 | 956 |
| December 2024 | 1,075 |
| November 2024 | 1,002 |
| October 2024 | 1,085 |
| September 2024 | 2,162 |
| August 2024 | 1,352 |
| July 2024 | 3,664 |
| June 2024 | 1,730 |
| May 2024 | 1,869 |
| April 2024 | 222 |
| March 2024 | 247 |
| February 2024 | 398 |
| January 2024 | 427 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Marble Falls plant, and when do they retire?
2 operable generators total 39.6 MW, with an average age of 74 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1950s | 2 | 40 | 100% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Conventional Hydroelectric | 20 | 1951 | n/a |
| 2 | Operating | Conventional Hydroelectric | 20 | 1951 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Marble Falls plant?
EIA lists no joint owners for Marble Falls. Lower Colorado River Authority operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Marble Falls plant?
Marble Falls is in Marble Falls, Burnet County, Texas, at 30.5553° N, 98.2576° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).
Source: EIA Form EIA-860, Plant, 2025 final.
Which hydro plants in Texas are similar in size?
Texas has 23 operable hydro plants with 735 MW of capacity, and Marble Falls' 39.6 MW is 5% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Granite Shoals | Burnet | 54 | 36,793 |
| Sam Rayburn Dam | Jasper | 52 | 207,948 |
| Whitney | Bosque | 42 | 66,931 |
| Marble Falls | Burnet | 40 | 23,788 |
| Falcon Dam & Power | Starr | 32 | 8,508 |
| RC Thomas Hydroelectric Project | Polk | 27 | 123,586 |
Source: EIA Forms EIA-860 and EIA-923, 2025.