Skip to main content
RateWatt

Hydro power plant, Texas

Whitney hydroelectric power plant, Texas

Whitney is a 41.8 MW hydro power plant in Bosque County, Texas, operated by USACE-Fort Worth District, and it generated 66,931 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 17th percentile of U.S. hydro plants. By 2025 generation it ranks 3,785th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

41.8 MWNameplate capacity
18%Capacity factor, 2025, 17th percentile, on 42 MW net summer
3,785thU.S. rank by generation, 2025
72 yearsAverage generator age, by MW

How hard does the Whitney plant run compared with other hydro plants?

The Whitney plant had a capacity factor of 18% in 2025 on 42 MW of net summer capacity, the 17th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 66 days at full output out of 365.

0%Shaded: the middle half of hydro plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Whitney18%
Hydro plants, 75th percentile44%
Hydro plants, median33%
Hydro plants, 25th percentile22%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Whitney plant generating more or less than last year?

Whitney generated 66,931 MWh in 2025; EIA reports no 2024 total to compare. 2024 has output for only 10 months, so the two years are not compared.

6 months show net generation below zero, when the plant used more power than it sent out, so the months are listed below rather than charted.

Net generation by period
PeriodMWh
202469,357
202566,931
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 2025-55
November 2025252
October 2025698
September 2025-63
August 2025-75
July 202515,303
June 202523,151
May 202516,336
April 20257,370
March 2025-47
February 20252,918
January 20251,143
December 2024915
November 2024375
October 20241,170
September 2024-62
August 2024-71
July 2024437
June 202425,163
May 202417,669
April 20246,854
March 20248,187
February 20247,771
January 2024949

Source: EIA Form EIA-923, through August 2026.

How much of Texas' electricity comes from the Whitney plant?

Whitney made 0.0% of the 592,896,176 MWh reported by Texas plants in 2025, from 0.0% of the state's 195,966 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 614th largest of 1,023 plants in Texas, the 4,048th largest of 14,327 in the U.S. and the 302nd largest of 1,393 hydro plants. By 2025 generation it is the 519th largest of 816 generating plants in the state.

Whitney within Texas, 2025
MeasureThis plantTexasShare
Capacity (MW)42195,9660.0%
Generation (MWh)66,931592,896,1760.0%
Hydro capacity (MW)427355.7%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Whitney plant, and when do they retire?

2 operable generators total 41.8 MW, with an average age of 72 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1950s242100%none reported
Every generator, 2 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingConventional Hydroelectric211953n/a
2OperatingConventional Hydroelectric211953n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Whitney plant?

EIA lists no joint owners for Whitney. USACE-Fort Worth District operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Whitney plant?

Whitney is in Clifton, Bosque County, Texas, at 31.8694° N, 97.3667° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).

Source: EIA Form EIA-860, Plant, 2025 final.

Which hydro plants in Texas are similar in size?

Texas has 23 operable hydro plants with 735 MW of capacity, and Whitney's 41.8 MW is 6% of that.

Hydro plants in Texas around this size
PlantCountyMW2025 MWh
Buchanan Dam (TX)Llano5529,157
Granite ShoalsBurnet5436,793
Sam Rayburn DamJasper52207,948
WhitneyBosque4266,931
Marble FallsBurnet4023,788
Falcon Dam & PowerStarr328,508
RC Thomas Hydroelectric ProjectPolk27123,586

Source: EIA Forms EIA-860 and EIA-923, 2025.