Skip to main content
RateWatt

Solar power plant, Kentucky

Martin County Solar Project, LLC power plant, Kentucky

Martin County Solar Project, LLC is a 111 MW solar power plant in Martin County, Kentucky, operated by Martin County Solar Project, LLC, and it generated 210,877 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.3% of the generation reported in Kentucky, and its capacity factor sits at the 39th percentile of U.S. solar plants. By 2025 generation it ranks 2,418th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

111 MWNameplate capacity
22%Capacity factor, 2025, 39th percentile, on 111 MW net summer
0.3%Of KY generation, 2025
1 yearAverage generator age, by MW

How hard does the Martin County Solar Project, LLC plant run compared with other solar plants?

The Martin County Solar Project, LLC plant had a capacity factor of 22% in 2025 on 111 MW of net summer capacity, the 39th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 79 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Martin County Solar Project, LLC22%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Martin County Solar Project, LLC plant generating more or less than last year?

Martin County Solar Project, LLC generated 210,877 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 5.4% ahead of the same months of 2025. 2024 has output for only 1 month, so the two years are not compared.

Net generation by period
PeriodMWh
20247,147
2025210,877
2026 through August161,819
2025, same months153,561
Monthly generation, Dec 2024 to Aug 2026
MonthMWh
August 202622,968
July 202624,806
June 202625,243
May 202623,627
April 202624,041
March 202618,489
February 202612,273
January 202610,372
December 20257,227
November 202510,889
October 202517,709
September 202521,491
August 202523,494
July 202524,377
June 202523,584
May 202521,036
April 202519,704
March 202519,387
February 202511,502
January 202510,477
December 20247,147

Source: EIA Form EIA-923, through August 2026.

How much of Kentucky's electricity comes from the Martin County Solar Project, LLC plant?

Martin County Solar Project, LLC made 0.3% of the 73,948,902 MWh reported by Kentucky plants in 2025, from 0.5% of the state's 22,180 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 27th largest of 62 plants in Kentucky, the 2,424th largest of 14,327 in the U.S. and the 397th largest of 7,223 solar plants. By 2025 generation it is the 28th largest of 59 generating plants in the state.

Martin County Solar Project, LLC within Kentucky, 2025
MeasureThis plantKentuckyShare
Capacity (MW)11122,1800.5%
Generation (MWh)210,87773,948,9020.3%
Solar capacity (MW)1111,1279.9%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Martin County Solar Project, LLC plant, and when do they retire?

1 operable generator totals 111 MW, with an average age of 1 year weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1111100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
USMTCOperatingSolar Photovoltaic1112024n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Martin County Solar Project, LLC plant?

EIA lists no joint owners for Martin County Solar Project, LLC. Martin County Solar Project, LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Martin County Solar Project, LLC plant?

Martin County Solar Project, LLC is in Pilgrim, Martin County, Kentucky, at 37.7655° N, 82.4741° W. It sits in the PJM Interconnection, LLC balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Kentucky are similar in size?

Kentucky has 18 operable solar plants with 1,127 MW of capacity, and Martin County Solar Project, LLC's 111 MW is 10% of that.

Solar plants in Kentucky around this size
PlantCountyMW2025 MWh
Green River SolarMeade200270,969
SR RussellvilleLogan173343,713
Unbridled SolarHenderson160311,763
Martin County Solar Project, LLCMartin111210,877
Bluebird Solar LLCHarrison10054,199

Source: EIA Forms EIA-860 and EIA-923, 2025.