Solar power plant, North Carolina
Meadows PV 1 solar power plant, North Carolina
Meadows PV 1 is a 20 MW solar power plant in Martin County, North Carolina, operated by Fresh Air Energy XVIII, LLC, and it generated 16,404 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 7th percentile of U.S. solar plants. By 2025 generation it ranks 5,467th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Meadows PV 1 plant run compared with other solar plants?
The Meadows PV 1 plant had a capacity factor of 9% in 2025 on 20 MW of net summer capacity, the 7th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 34 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Meadows PV 1 | 9% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Meadows PV 1 plant generating more or less than last year?
Meadows PV 1 generated 16,404 MWh in 2025; EIA reports no 2024 total to compare. 2024 has output for only 11 months, so the two years are not compared.
| Period | MWh |
|---|---|
| 2024 | 4,971 |
| 2025 | 16,404 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 1,405 |
| November 2025 | 1,982 |
| October 2025 | 1,994 |
| September 2025 | 1,912 |
| August 2025 | 1,883 |
| July 2025 | 1,618 |
| June 2025 | 1,473 |
| May 2025 | 1,261 |
| April 2025 | 1,242 |
| March 2025 | 899 |
| February 2025 | 320 |
| January 2025 | 415 |
| December 2024 | 357 |
| November 2024 | 412 |
| October 2024 | 348 |
| September 2024 | 432 |
| August 2024 | 534 |
| July 2024 | 506 |
| June 2024 | 628 |
| May 2024 | 40 |
| April 2024 | 0 |
| March 2024 | 354 |
| February 2024 | 710 |
| January 2024 | 650 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Meadows PV 1 plant, and when do they retire?
1 operable generator totals 20 MW, with an average age of 9 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 20 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| MEAD1 | Operating | Solar Photovoltaic | 20 | 2016 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Meadows PV 1 plant?
EIA lists no joint owners for Meadows PV 1. Fresh Air Energy XVIII, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Meadows PV 1 plant?
Meadows PV 1 is in Williamston, Martin County, North Carolina, at 35.8369° N, 77.1269° W. It sits in the PJM Interconnection, LLC balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in North Carolina are similar in size?
North Carolina has 757 operable solar plants with 7,025 MW of capacity, and Meadows PV 1's 20 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Halifax (NC) | Halifax | 20 | 33,378 |
| Watson Seed Farm PV1 | Nash | 20 | 29,849 |
| Shawboro PV1 | Currituck | 20 | 34,891 |
| Meadows PV 1 | Martin | 20 | 16,404 |
| Grandy PV 1 | Currituck | 20 | 24,854 |
| Kelford (Duke) | Bertie | 20 | 40,272 |
| Pasquotank | Pasquotank | 20 | 33,980 |
Source: EIA Forms EIA-860 and EIA-923, 2025.