Coal power plant, Wyoming
Neil Simpson II coal power plant, Wyoming
Neil Simpson II is a 130 MW power plant, 90 MW of it coal, in Campbell County, Wyoming, operated by Black Hills Power, Inc., and it generated 641,838 MWh in 2025 (Forms EIA-860 and EIA-923). That is 1.4% of the generation reported in Wyoming, and its capacity factor sits at the 91st percentile of U.S. coal plants. By 2025 generation it ranks 1,071st of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Neil Simpson II plant run compared with other coal plants?
The Neil Simpson II plant's coal units had a capacity factor of 73% in 2025 on 82 MW of net summer capacity, the 91st percentile of the 181 U.S. coal plants with at least 20 MW. The typical coal plant reached 49%. That equals about 267 days at full output out of 365.
0%Shaded: the middle half of coal plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Neil Simpson II | 73% |
| Coal plants, 75th percentile | 63% |
| Coal plants, median | 49% |
| Coal plants, 25th percentile | 37% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its coal generators only. Values above 105% are left out of the comparison.
Is the Neil Simpson II plant generating more or less than last year?
Generation at Neil Simpson II fell 2.9% from 2024 to 2025, from 660,905 MWh to 641,838 MWh.
| Period | MWh |
|---|---|
| 2024 | 660,905 |
| 2025 | 641,838 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 50,441 |
| November 2025 | 46,177 |
| October 2025 | 5,037 |
| September 2025 | 46,856 |
| August 2025 | 66,578 |
| July 2025 | 65,606 |
| June 2025 | 64,938 |
| May 2025 | 59,207 |
| April 2025 | 56,065 |
| March 2025 | 60,165 |
| February 2025 | 58,181 |
| January 2025 | 62,588 |
| December 2024 | 60,869 |
| November 2024 | 50,724 |
| October 2024 | 55,380 |
| September 2024 | 52,380 |
| August 2024 | 60,386 |
| July 2024 | 56,543 |
| June 2024 | 55,164 |
| May 2024 | 26,407 |
| April 2024 | 55,597 |
| March 2024 | 62,750 |
| February 2024 | 60,021 |
| January 2024 | 64,685 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Neil Simpson II plant, and when do they retire?
2 operable generators total 130 MW, with an average age of 28 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1990s | 1 | 90 | 69% | none reported |
| 2000s | 1 | 40 | 31% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 2 | Operating | Conventional Steam Coal | 90 | 1995 | n/a |
| GT1 | Operating | Natural Gas Fired Combustion Turbine | 40 | 2000 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Neil Simpson II plant?
EIA lists no joint owners for Neil Simpson II. Black Hills Power, Inc. operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What does Black Hills Power, Inc. charge homes?
Black Hills Power, Inc., the operator of Neil Simpson II, had an average residential price of 13.77¢ per kWh and an average bill of $106 a month in 2025, 3% above the Wyoming average of 13.37¢.
| Measure | Price | Monthly bill | Against Wyoming |
|---|---|---|---|
| Black Hills Power, Inc. | 13.77¢ | $106 | 3% higher |
| Wyoming average | 13.37¢ | $112 | |
| U.S. average | 17.23¢ | $151 | 29% higher |
Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.
What fuels does the Neil Simpson II plant use?
Neil Simpson II has capacity on 2 fuels: 69% coal and 31% natural gas. In 2025, coal made 82% of its output.
| Fuel | MW | Share | 2025 MWh |
|---|---|---|---|
| Coal | 90 | 69.2% | 525,888 |
| Natural gas | 40 | 30.8% | 115,950 |
Source: EIA Forms EIA-860 and EIA-923, 2025.
Where is the Neil Simpson II plant?
Neil Simpson II is in Gillette, Campbell County, Wyoming, at 44.2856° N, 105.3833° W. It sits in the Western Area Power Administration - Rocky Mountain Region balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which coal plants in Wyoming are similar in size?
Source: EIA Forms EIA-860 and EIA-923, 2025.