Skip to main content
RateWatt

Wind power plant, Missouri

North Fork Ridge Wind Energy Center, Missouri

North Fork Ridge Wind Energy Center is a 149 MW wind power plant in Barton County, Missouri, operated by Empire District Electric Co, and it generated 489,788 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.7% of the generation reported in Missouri, and its capacity factor sits at the 68th percentile of U.S. wind plants. By 2025 generation it ranks 1,360th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

149 MWNameplate capacity
38%Capacity factor, 2025, 68th percentile, on 146 MW net summer
0.7%Of MO generation, 2025
5 yearsAverage generator age, by MW

How hard does the North Fork Ridge Wind Energy Center plant run compared with other wind plants?

The North Fork Ridge Wind Energy Center plant had a capacity factor of 38% in 2025 on 146 MW of net summer capacity, the 68th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 140 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
North Fork Ridge Wind Energy Center38%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the North Fork Ridge Wind Energy Center plant generating more or less than last year?

Generation at North Fork Ridge Wind Energy Center fell 6.4% from 2024 to 2025, from 523,507 MWh to 489,788 MWh. Through August 2026 it is running 22.4% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024523,507
2025489,788
2026 through August393,391
2025, same months321,508
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202638,108
July 202630,030
June 202645,867
May 202640,738
April 202663,068
March 202668,446
February 202650,603
January 202656,531
December 202561,575
November 202546,619
October 202544,544
September 202515,542
August 202522,800
July 202529,504
June 202533,691
May 202531,683
April 202553,483
March 202562,288
February 202546,595
January 202541,464
December 202446,336
November 202452,858
October 202431,283
September 202431,841
August 202429,349
July 202434,936
June 202441,718
May 202436,851
April 202462,452
March 202459,974
February 202461,170
January 202434,739

Source: EIA Form EIA-923, through August 2026.

How much of Missouri's electricity comes from the North Fork Ridge Wind Energy Center plant?

North Fork Ridge Wind Energy Center made 0.7% of the 71,443,096 MWh reported by Missouri plants in 2025, from 0.6% of the state's 23,215 MW of capacity. By capacity it is the 40th largest of 137 plants in Missouri, the 2,067th largest of 14,327 in the U.S. and the 484th largest of 1,358 wind plants. By 2025 generation it is the 20th largest of 122 generating plants in the state.

North Fork Ridge Wind Energy Center within Missouri, 2025
MeasureThis plantMissouriShare
Capacity (MW)14923,2150.6%
Generation (MWh)489,78871,443,0960.7%
Wind capacity (MW)1492,4546.1%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the North Fork Ridge Wind Energy Center plant, and when do they retire?

1 operable generator totals 149 MW, with an average age of 5 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1149100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
NFRW1OperatingOnshore Wind Turbine1492020n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the North Fork Ridge Wind Energy Center plant?

EIA lists no joint owners for North Fork Ridge Wind Energy Center. Empire District Electric Co operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Empire District Electric Co charge homes?

Empire District Electric Co, the operator of North Fork Ridge Wind Energy Center, had an average residential price of 14.77¢ per kWh and an average bill of $154 a month in 2025, 11% above the Missouri average of 13.30¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Missouri
Empire District Electric Co14.77¢$15411% higher
Missouri average13.30¢$138
U.S. average17.23¢$15130% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the North Fork Ridge Wind Energy Center plant?

North Fork Ridge Wind Energy Center is in Mindenmines, Barton County, Missouri, at 37.3900° N, 94.5103° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in Missouri are similar in size?

Missouri has 14 operable wind plants with 2,454 MW of capacity, and North Fork Ridge Wind Energy Center's 149 MW is 6% of that.

Wind plants in Missouri around this size
PlantCountyMW2025 MWh
Osborn Wind EnergyDeKalb201671,868
Lost Creek Wind Energy FacilityDeKalb168380,290
Kings Point Wind Energy CenterLawrence149502,606
North Fork Ridge Wind Energy CenterBarton149489,788
Farmers City Wind LLCAtchison146253,025

Source: EIA Forms EIA-860 and EIA-923, 2025.