Skip to main content
RateWatt

Wind power plant, Missouri

Lost Creek Wind Energy Facility, Missouri

Lost Creek Wind Energy Facility is a 168 MW wind power plant in DeKalb County, Missouri, operated by Pattern Operators LP, and it generated 380,290 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.5% of the generation reported in Missouri, and its capacity factor sits at the 24th percentile of U.S. wind plants. By 2025 generation it ranks 1,651st of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

168 MWNameplate capacity
26%Capacity factor, 2025, 24th percentile, on 168 MW net summer
0.5%Of MO generation, 2025
15 yearsAverage generator age, by MW

How hard does the Lost Creek Wind Energy Facility plant run compared with other wind plants?

The Lost Creek Wind Energy Facility plant had a capacity factor of 26% in 2025 on 168 MW of net summer capacity, the 24th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 94 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Lost Creek Wind Energy Facility26%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Lost Creek Wind Energy Facility plant generating more or less than last year?

Generation at Lost Creek Wind Energy Facility fell 4.6% from 2024 to 2025, from 398,803 MWh to 380,290 MWh. Through August 2026 it is running 3.9% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024398,803
2025380,290
2026 through August270,046
2025, same months259,823
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202620,914
July 202613,392
June 202625,523
May 202628,448
April 202651,851
March 202654,960
February 202634,149
January 202640,809
December 202539,009
November 202535,564
October 202532,359
September 202513,535
August 202515,089
July 202516,213
June 202523,453
May 202526,196
April 202544,109
March 202554,892
February 202537,914
January 202541,957
December 202436,304
November 202435,095
October 202441,091
September 202420,910
August 202418,796
July 202416,994
June 202429,489
May 202426,542
April 202452,502
March 202448,220
February 202439,084
January 202433,776

Source: EIA Form EIA-923, through August 2026.

How much of Missouri's electricity comes from the Lost Creek Wind Energy Facility plant?

Lost Creek Wind Energy Facility made 0.5% of the 71,443,096 MWh reported by Missouri plants in 2025, from 0.7% of the state's 23,215 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 36th largest of 137 plants in Missouri, the 1,841st largest of 14,327 in the U.S. and the 385th largest of 1,358 wind plants. By 2025 generation it is the 25th largest of 122 generating plants in the state.

Lost Creek Wind Energy Facility within Missouri, 2025
MeasureThis plantMissouriShare
Capacity (MW)16823,2150.7%
Generation (MWh)380,29071,443,0960.5%
Wind capacity (MW)1682,4546.8%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Lost Creek Wind Energy Facility plant, and when do they retire?

1 operable generator totals 168 MW, with an average age of 15 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s1168100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
LCWOperatingOnshore Wind Turbine1682010n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Lost Creek Wind Energy Facility plant?

EIA lists no joint owners for Lost Creek Wind Energy Facility. Pattern Operators LP operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Lost Creek Wind Energy Facility plant?

Lost Creek Wind Energy Facility is in King City, DeKalb County, Missouri, at 39.9814° N, 94.5181° W. It sits in the Associated Electric Cooperative, Inc. balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in Missouri are similar in size?

Missouri has 14 operable wind plants with 2,454 MW of capacity, and Lost Creek Wind Energy Facility's 168 MW is 7% of that.

Wind plants in Missouri around this size
PlantCountyMW2025 MWh
Clear Creek WindNodaway242466,222
White Cloud Wind Project, LLCNodaway237828,191
Osborn Wind EnergyDeKalb201671,868
Lost Creek Wind Energy FacilityDeKalb168380,290
Kings Point Wind Energy CenterLawrence149502,606
North Fork Ridge Wind Energy CenterBarton149489,788
Farmers City Wind LLCAtchison146253,025

Source: EIA Forms EIA-860 and EIA-923, 2025.