Skip to main content
RateWatt

Solar power plant, Texas

Oberon IB solar power plant, Texas

Oberon IB is a 30 MW solar power plant in Ector County, Texas, operated by Oberon Solar IB, and it generated 61,946 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 54th percentile of U.S. solar plants. By 2025 generation it ranks 3,849th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

30 MWNameplate capacity
24%Capacity factor, 2025, 54th percentile, on 30 MW net summer
3,849thU.S. rank by generation, 2025
5 yearsAverage generator age, by MW

How hard does the Oberon IB plant run compared with other solar plants?

The Oberon IB plant had a capacity factor of 24% in 2025 on 30 MW of net summer capacity, the 54th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 86 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Oberon IB24%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Oberon IB plant generating more or less than last year?

Generation at Oberon IB rose 14.7% from 2024 to 2025, from 54,002 MWh to 61,946 MWh. Through August 2026 it is running 34.2% behind the same months of 2025.

Net generation by period
PeriodMWh
202454,002
202561,946
2026 through August30,139
2025, same months45,779
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 20267,599
July 20266,902
June 20264,110
May 20265,206
April 20261,058
March 20261,898
February 2026962
January 20262,404
December 20252,766
November 20253,900
October 20255,223
September 20254,278
August 20256,987
July 20257,331
June 20255,764
May 20256,943
April 20255,923
March 20254,260
February 20254,932
January 20253,639
December 20243,414
November 20243,260
October 20244,707
September 20244,597
August 20246,641
July 20243,395
June 20246,614
May 20245,689
April 20244,241
March 20244,574
February 20243,435
January 20243,435

Source: EIA Form EIA-923, through August 2026.

How much of Texas' electricity comes from the Oberon IB plant?

Oberon IB made 0.0% of the 592,896,176 MWh reported by Texas plants in 2025, from 0.0% of the state's 195,966 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 629th largest of 1,023 plants in Texas, the 4,354th largest of 14,327 in the U.S. and the 1,027th largest of 7,223 solar plants. By 2025 generation it is the 522nd largest of 816 generating plants in the state.

Oberon IB within Texas, 2025
MeasureThis plantTexasShare
Capacity (MW)30195,9660.0%
Generation (MWh)61,946592,896,1760.0%
Solar capacity (MW)3030,7390.1%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Oberon IB plant, and when do they retire?

1 operable generator totals 30 MW, with an average age of 5 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s130100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
OBR1BOperatingSolar Photovoltaic302020n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Oberon IB plant?

174 Power Global Corp. is the only joint owner reported for Oberon IB, with 100.0%. Oberon Solar IB operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Oberon IB plant?

Oberon IB is in Odessa, Ector County, Texas, at 31.6924° N, 102.6974° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Texas are similar in size?

Texas has 225 operable solar plants with 30,739 MW of capacity, and Oberon IB's 30 MW is 0% of that.

Solar plants in Texas around this size
PlantCountyMW2025 MWh
Barilla SolarPecos3052,945
Webberville Solar ProjectTravis3056,362
Bluebell SolarSterling3071,759
Oberon IBEctor3061,946
Hayhurst Texas SolarCulberson2570,129
Oxy Renewable Energy - GoldsmithEctor1738,798
Phantom SolarBell158,079

Source: EIA Forms EIA-860 and EIA-923, 2025.