Skip to main content
RateWatt

Biomass power plant, Florida

Pasco Cnty Solid Waste Resource Recovery biomass power plant, Florida

Pasco Cnty Solid Waste Resource Recovery is a 31.2 MW biomass power plant in Pasco County, Florida, operated by Pasco County-(FL), and it generated 180,606 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Florida, and its capacity factor sits at the 26th percentile of U.S. biomass plants. By 2025 generation it ranks 2,643rd of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

31.2 MWNameplate capacity
36%Capacity factor, 2025, 26th percentile, on 26 MW net summer
0.1%Of FL generation, 2025
34 yearsAverage generator age, by MW

How hard does the Pasco Cnty Solid Waste Resource Recovery plant run compared with other biomass plants?

The Pasco Cnty Solid Waste Resource Recovery plant had a capacity factor of 36% in 2025 on 26 MW of net summer capacity, the 26th percentile of the 167 U.S. biomass plants with at least 20 MW. The typical biomass plant reached 48%. That equals about 130 days at full output out of 365.

0%Shaded: the middle half of biomass plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Pasco Cnty Solid Waste Resource Recovery36%
Biomass plants, 75th percentile65%
Biomass plants, median48%
Biomass plants, 25th percentile35%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Pasco Cnty Solid Waste Resource Recovery plant generating more or less than last year?

Generation at Pasco Cnty Solid Waste Resource Recovery fell 1.4% from 2024 to 2025, from 183,232 MWh to 180,606 MWh. Through August 2026 it is running 6.5% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024183,232
2025180,606
2026 through August128,113
2025, same months120,276
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202616,480
July 202616,733
June 202616,307
May 202616,555
April 202616,630
March 202612,524
February 202615,802
January 202617,082
December 202517,487
November 202516,583
October 202510,677
September 202515,583
August 202514,577
July 202516,657
June 202515,894
May 202515,865
April 202515,692
March 20259,301
February 202514,635
January 202517,655
December 202417,565
November 202415,019
October 202410,904
September 202415,507
August 202416,847
July 202416,852
June 202416,466
May 202410,877
April 202416,257
March 202414,495
February 202415,168
January 202417,275

Source: EIA Form EIA-923, through August 2026.

How much of Florida's electricity comes from the Pasco Cnty Solid Waste Resource Recovery plant?

Pasco Cnty Solid Waste Resource Recovery made 0.1% of the 267,867,735 MWh reported by Florida plants in 2025, from 0.0% of the state's 79,936 MW of capacity. Its share of output is 1.7 times its share of capacity. By capacity it is the 251st largest of 331 plants in Florida, the 4,326th largest of 14,327 in the U.S. and the 137th largest of 585 biomass plants. By 2025 generation it is the 94th largest of 313 generating plants in the state.

Pasco Cnty Solid Waste Resource Recovery within Florida, 2025
MeasureThis plantFloridaShare
Capacity (MW)3179,9360.0%
Generation (MWh)180,606267,867,7350.1%
Biomass capacity (MW)311,1442.7%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Pasco Cnty Solid Waste Resource Recovery plant, and when do they retire?

1 operable generator totals 31.2 MW, with an average age of 34 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860. 1 more is proposed, totalling 17 MW.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1990s131100%none reported
Every generator, 2 in all
UnitStatusTechnologyMWIn servicePlanned retirement
GEN1OperatingMunicipal Solid Waste311991n/a
GEN2Under construction, under half builtMunicipal Solid Waste172027n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Pasco Cnty Solid Waste Resource Recovery plant?

EIA lists no joint owners for Pasco Cnty Solid Waste Resource Recovery. Pasco County-(FL) operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Pasco Cnty Solid Waste Resource Recovery plant?

Pasco Cnty Solid Waste Resource Recovery is in Spring Hill, Pasco County, Florida, at 28.3681° N, 82.5583° W. It sits in the Progress Energy Florida balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which biomass plants in Florida are similar in size?

Florida has 29 operable biomass plants with 1,144 MW of capacity, and Pasco Cnty Solid Waste Resource Recovery's 31.2 MW is 3% of that.

Biomass plants in Florida around this size
PlantCountyMW2025 MWh
Clewiston Sugar HouseHendry49260,932
Hillsborough County Resource RecoveryHillsborough4790,482
Fernandina PlantNassau42150,268
Pasco Cnty Solid Waste Resource RecoveryPasco3181,003
McKay Bay FacilityHillsborough2244,909

Source: EIA Forms EIA-860 and EIA-923, 2025.