Solar power plant, Florida

Pelican Solar Center, Florida

Pelican Solar Center is a 74.5 MW solar power plant in St Lucie County, Florida, operated by Florida Power & Light Co, and it generated 151,334 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Florida, and its capacity factor sits at the 50th percentile of U.S. solar plants. By 2025 generation it ranks 2,894th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

74.5 MWNameplate capacity
23%Capacity factor, 2025, 50th percentile, on 74.5 MW net summer
0.1%Of FL generation, 2025
4 yearsAverage generator age, by MW

How hard does the Pelican Solar Center plant run compared with other solar plants?

The Pelican Solar Center plant had a capacity factor of 23% in 2025 on 74.5 MW of net summer capacity, the 50th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 85 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Pelican Solar Center23%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Pelican Solar Center plant generating more or less than last year?

Generation at Pelican Solar Center fell 0.4% from 2024 to 2025, from 151,955 MWh to 151,334 MWh. Through August 2026 it is running 7.3% behind the same months of 2025.

Net generation by period
PeriodMWh
2024151,955
2025151,334
2026 through August98,020
2025, same months105,735
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202612,246
July 202613,052
June 202612,895
May 202614,455
April 202613,907
March 202613,278
February 20269,870
January 20268,317
December 202511,201
November 202511,416
October 202512,144
September 202510,838
August 202513,010
July 202513,171
June 202513,122
May 202514,226
April 202515,745
March 202514,804
February 202511,571
January 202510,086
December 202410,613
November 202410,734
October 202411,430
September 202411,867
August 202412,601
July 202413,727
June 202412,909
May 202415,809
April 202416,201
March 202414,110
February 202412,930
January 20249,024

Source: EIA Form EIA-923, through August 2026.

How much of Florida's electricity comes from the Pelican Solar Center plant?

Pelican Solar Center made 0.1% of the 267,867,735 MWh reported by Florida plants in 2025, from 0.1% of the state's 79,936 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 105th largest of 331 plants in Florida, the 3,163rd largest of 14,327 in the U.S. and the 661st largest of 7,223 solar plants. By 2025 generation it is the 152nd largest of 313 generating plants in the state.

Pelican Solar Center within Florida, 2025
MeasureThis plantFloridaShare
Capacity (MW)7579,9360.1%
Generation (MWh)151,334267,867,7350.1%
Solar capacity (MW)7512,2230.6%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Pelican Solar Center plant, and when do they retire?

1 operable generator totals 74.5 MW, with an average age of 4 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s175100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingSolar Photovoltaic752021n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Pelican Solar Center plant?

EIA lists no joint owners for Pelican Solar Center. Florida Power & Light Co operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Florida Power & Light Co charge homes?

Florida Power & Light Co, the operator of Pelican Solar Center, had an average residential price of 14.62¢ per kWh and an average bill of $162 a month in 2025, 4% below the Florida average of 15.21¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Florida
Florida Power & Light Co14.62¢$1624% lower
Florida average15.21¢$168
U.S. average17.23¢$15113% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Pelican Solar Center plant?

Pelican Solar Center is in Ft. Pierce, St Lucie County, Florida, at 27.5220° N, 80.5473° W. It sits in the Florida Power & Light Company balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Florida are similar in size?

Florida has 210 operable solar plants with 12,223 MW of capacity, and Pelican Solar Center's 74.5 MW is 1% of that.

Solar plants in Florida around this size
PlantCountyMW2025 MWh
Palm Bay SolarBrevard75150,270
Lakeside Solar CenterOkeechobee75148,979
Union Springs Solar CenterUnion75148,690
Pelican Solar CenterSt Lucie75151,334
Egret Solar CenterBaker75127,114
Discovery Solar CenterBrevard75139,484
Sabal Palm Solar CenterPalm Beach75156,870