Solar power plant, Arkansas
Quartz Solar, LLC power plant, Arkansas
Quartz Solar, LLC is a 135 MW solar power plant in Cross County, Arkansas, operated by RWE Clean Energy, and it generated 292,992 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.4% of the generation reported in Arkansas, and its capacity factor sits at the 63rd percentile of U.S. solar plants. By 2025 generation it ranks 2,007th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Quartz Solar, LLC plant run compared with other solar plants?
The Quartz Solar, LLC plant had a capacity factor of 25% in 2025 on 135 MW of net summer capacity, the 63rd percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 90 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Quartz Solar, LLC | 25% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Quartz Solar, LLC plant generating more or less than last year?
Quartz Solar, LLC generated 292,992 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 0.3% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | n/a |
| 2025 | 292,992 |
| 2026 through August | 214,401 |
| 2025, same months | 213,708 |
Monthly generation, Jan 2025 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 34,130 |
| July 2026 | 33,297 |
| June 2026 | 29,724 |
| May 2026 | 29,164 |
| April 2026 | 25,728 |
| March 2026 | 24,079 |
| February 2026 | 19,632 |
| January 2026 | 18,647 |
| December 2025 | 11,924 |
| November 2025 | 16,708 |
| October 2025 | 23,633 |
| September 2025 | 27,019 |
| August 2025 | 33,161 |
| July 2025 | 36,230 |
| June 2025 | 32,690 |
| May 2025 | 25,722 |
| April 2025 | 28,019 |
| March 2025 | 25,904 |
| February 2025 | 17,027 |
| January 2025 | 14,955 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Quartz Solar, LLC plant, and when do they retire?
1 operable generator totals 135 MW, with an average age of 0 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 135 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| QRTZ | Operating | Solar Photovoltaic | 135 | 2025 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Quartz Solar, LLC plant?
EIA lists no joint owners for Quartz Solar, LLC. RWE Clean Energy operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Quartz Solar, LLC plant?
Quartz Solar, LLC is in Wynne, Cross County, Arkansas, at 35.2085° N, 90.7912° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Arkansas are similar in size?
Arkansas has 65 operable solar plants with 2,534 MW of capacity, and Quartz Solar, LLC's 135 MW is 5% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Newport Solar Project | Jackson | 180 | 356,412 |
| Crooked Lake Solar, LLC | Mississippi | 175 | 393,495 |
| Driver Solar | Mississippi | 150 | 419,056 |
| Quartz Solar, LLC | Cross | 135 | 292,992 |
| Woodruff County Solar | Woodruff | 122 | 203,703 |
| Prairie Mist Solar | Ashley | 109 | 232,039 |
| Searcy Solar Hybrid | White | 100 | 193,180 |