Solar power plant, California

RE Barren Ridge 1 solar power plant, California

RE Barren Ridge 1 is a 60 MW solar power plant in Kern County, California, operated by RE Barren Ridge 1, LLC, and it generated 164,367 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in California, and its capacity factor sits at the 95th percentile of U.S. solar plants. By 2025 generation it ranks 2,768th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

60 MWNameplate capacity
31%Capacity factor, 2025, 95th percentile, on 60 MW net summer
0.1%Of CA generation, 2025
9 yearsAverage generator age, by MW

How hard does the RE Barren Ridge 1 plant run compared with other solar plants?

The RE Barren Ridge 1 plant had a capacity factor of 31% in 2025 on 60 MW of net summer capacity, the 95th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 114 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
RE Barren Ridge 131%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the RE Barren Ridge 1 plant generating more or less than last year?

Generation at RE Barren Ridge 1 fell 6.1% from 2024 to 2025, from 174,985 MWh to 164,367 MWh.

Net generation by period
PeriodMWh
2024174,985
2025164,367
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 20257,779
November 20257,891
October 202513,212
September 202514,495
August 202517,289
July 202519,920
June 202517,991
May 202519,063
April 202516,446
March 20259,838
February 202510,458
January 20259,985
December 20248,164
November 20249,864
October 202413,233
September 202415,452
August 202418,384
July 202418,917
June 202419,821
May 202420,019
April 202418,406
March 202414,201
February 20249,913
January 20248,611

Source: EIA Form EIA-923, through August 2026.

How much of California's electricity comes from the RE Barren Ridge 1 plant?

RE Barren Ridge 1 made 0.1% of the 204,542,898 MWh reported by California plants in 2025, from 0.1% of the state's 107,433 MW of capacity. Its share of output is 1.4 times its share of capacity. By capacity it is the 378th largest of 1,877 plants in California, the 3,517th largest of 14,327 in the U.S. and the 806th largest of 7,223 solar plants. By 2025 generation it is the 280th largest of 1,608 generating plants in the state.

RE Barren Ridge 1 within California, 2025
MeasureThis plantCaliforniaShare
Capacity (MW)60107,4330.1%
Generation (MWh)164,367204,542,8980.1%
Solar capacity (MW)6024,6630.2%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the RE Barren Ridge 1 plant, and when do they retire?

1 operable generator totals 60 MW, with an average age of 9 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s160100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
REBR1OperatingSolar Photovoltaic602016n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the RE Barren Ridge 1 plant?

EIA lists no joint owners for RE Barren Ridge 1. RE Barren Ridge 1, LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the RE Barren Ridge 1 plant?

RE Barren Ridge 1 is in Mojave, Kern County, California, at 35.2047° N, 118.0687° W. It sits in the Los Angeles Department of Water and Power balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in California are similar in size?

California has 934 operable solar plants with 24,663 MW of capacity, and RE Barren Ridge 1's 60 MW is 0% of that.

Solar plants in California around this size
PlantCountyMW2025 MWh
North Star SolarFresno62133,232
Regulus Solar ProjectKern60149,746
Five Points Solar ParkFresno6080,718
RE Barren Ridge 1Kern60164,367
SF Azalea, LLCKern6044
Hecate Energy Beacon Solar 1Kern56128,675
Hecate Energy Beacon Solar 3Kern56122,062

Source: EIA Forms EIA-860 and EIA-923, 2025.