RE Gaskell West 4 LLC solar power plant, California

RE Gaskell West 4 LLC is a 20 MW solar power plant in Kern County, California, operated by RE Gaskell West LLC, and it generated 47,509 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 78th percentile of U.S. solar plants. By 2025 generation it ranks 4,160th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

20 MWNameplate capacity
27%Capacity factor, 2025, 78th percentile, on 20 MW net summer
4,160thU.S. rank by generation, 2025
2 yearsAverage generator age, by MW

How hard does the RE Gaskell West 4 LLC plant run compared with other solar plants?

The RE Gaskell West 4 LLC plant had a capacity factor of 27% in 2025 on 20 MW of net summer capacity, the 78th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 99 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
RE Gaskell West 4 LLC27%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the RE Gaskell West 4 LLC plant generating more or less than last year?

Generation at RE Gaskell West 4 LLC fell 5.0% from 2024 to 2025, from 50,002 MWh to 47,509 MWh.

Net generation by period
PeriodMWh
202450,002
202547,509
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 20252,901
November 20252,692
October 20253,911
September 20255,126
August 20256,396
July 20257,147
June 20255,803
May 20254,456
April 20252,661
March 20251,273
February 20251,584
January 20253,559
December 20243,089
November 20242,702
October 20243,240
September 20244,978
August 20242,848
July 20246,867
June 20246,799
May 20245,992
April 20244,053
March 20243,730
February 20243,013
January 20242,691

Source: EIA Form EIA-923, through August 2026.

How much of California's electricity comes from the RE Gaskell West 4 LLC plant?

RE Gaskell West 4 LLC made 0.0% of the 204,542,898 MWh reported by California plants in 2025, from 0.0% of the state's 107,433 MW of capacity. Its share of output is 1.2 times its share of capacity. By capacity it is the 619th largest of 1,877 plants in California, the 4,775th largest of 14,327 in the U.S. and the 1,198th largest of 7,223 solar plants. By 2025 generation it is the 474th largest of 1,608 generating plants in the state.

RE Gaskell West 4 LLC within California, 2025
MeasureThis plantCaliforniaShare
Capacity (MW)20107,4330.0%
Generation (MWh)47,509204,542,8980.0%
Solar capacity (MW)2024,6630.1%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the RE Gaskell West 4 LLC plant, and when do they retire?

1 operable generator totals 20 MW, with an average age of 2 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s120100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
PV4OperatingSolar Photovoltaic202023n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the RE Gaskell West 4 LLC plant?

EIA lists no joint owners for RE Gaskell West 4 LLC. RE Gaskell West LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the RE Gaskell West 4 LLC plant?

RE Gaskell West 4 LLC is in Rosamond, Kern County, California, at 34.8279° N, 118.5682° W. It sits in the California Independent System Operator balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in California are similar in size?

California has 934 operable solar plants with 24,663 MW of capacity, and RE Gaskell West 4 LLC's 20 MW is 0% of that.

Solar plants in California around this size
PlantCountyMW2025 MWh
Antelope DSR 3Los Angeles2055,108
Gaskell West 1 Solar FacilityKern2055,559
RE Gaskell West 3 LLCKern2050,755
RE Gaskell West 4 LLCKern2047,509
RE Gaskell West 5 LLCKern2047,998
Little Bear 3Fresno2020,047
Wister SolarImperial2033,044