Skip to main content
RateWatt

Solar power plant, California

RE Kent South, LLC solar power plant, California

RE Kent South, LLC is a 20 MW solar power plant in Kings County, California, operated by Onward Energy, and it generated 35,670 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 28th percentile of U.S. solar plants. By 2025 generation it ranks 4,512th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

20 MWNameplate capacity
20%Capacity factor, 2025, 28th percentile, on 20 MW net summer
4,512thU.S. rank by generation, 2025
11 yearsAverage generator age, by MW

How hard does the RE Kent South, LLC plant run compared with other solar plants?

The RE Kent South, LLC plant had a capacity factor of 20% in 2025 on 20 MW of net summer capacity, the 28th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 74 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
RE Kent South, LLC20%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the RE Kent South, LLC plant generating more or less than last year?

Generation at RE Kent South, LLC fell 19.4% from 2024 to 2025, from 44,265 MWh to 35,670 MWh.

Net generation by period
PeriodMWh
202444,265
202535,670
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 2025831
November 20251,596
October 20253,203
September 20252,869
August 20253,616
July 20253,593
June 20254,722
May 20254,768
April 20253,442
March 20252,966
February 20252,210
January 20251,854
December 20241,248
November 20242,231
October 20243,220
September 20244,006
August 20244,661
July 20244,761
June 20245,208
May 20245,980
April 20244,920
March 20243,852
February 20242,497
January 20241,681

Source: EIA Form EIA-923, through August 2026.

How much of California's electricity comes from the RE Kent South, LLC plant?

RE Kent South, LLC made 0.0% of the 204,542,898 MWh reported by California plants in 2025, from 0.0% of the state's 107,433 MW of capacity. By capacity it is the 619th largest of 1,877 plants in California, the 4,775th largest of 14,327 in the U.S. and the 1,111th largest of 7,223 solar plants. By 2025 generation it is the 554th largest of 1,608 generating plants in the state.

RE Kent South, LLC within California, 2025
MeasureThis plantCaliforniaShare
Capacity (MW)20107,4330.0%
Generation (MWh)35,670204,542,8980.0%
Solar capacity (MW)2024,6630.1%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the RE Kent South, LLC plant, and when do they retire?

1 operable generator totals 20 MW, with an average age of 11 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s120100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingSolar Photovoltaic202014n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the RE Kent South, LLC plant?

EIA lists no joint owners for RE Kent South, LLC. Onward Energy operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the RE Kent South, LLC plant?

RE Kent South, LLC is in Lemoore, Kings County, California, at 36.2261° N, 119.9053° W. It sits in the California Independent System Operator balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in California are similar in size?

California has 934 operable solar plants with 24,663 MW of capacity, and RE Kent South, LLC's 20 MW is 0% of that.

Solar plants in California around this size
PlantCountyMW2025 MWh
Western Antelope Blue Sky Ranch ALos Angeles2043,001
RE Kansas Solar, LLCKings2023,996
RE Old River One, LLCKern2037,520
RE Kent South, LLCKings2035,670
Calipatria Solar FarmImperial2036,119
CID Solar, LLCKings2040,678
Lone Valley Solar Park II LLCSan Bernardino2053,128

Source: EIA Forms EIA-860 and EIA-923, 2025.