Red Bud Solar Plant, North Carolina

Red Bud Solar Plant is a 80 MW solar power plant in Nash County, North Carolina, operated by Duke Energy Carolinas, LLC, and it generated 27,602 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 4th percentile of U.S. solar plants. By 2025 generation it ranks 4,847th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

80 MWNameplate capacity
4%Capacity factor, 2025, 4th percentile, on 80 MW net summer
4,847thU.S. rank by generation, 2025
Under 1 yearAverage generator age, by MW

How hard does Red Bud Solar Plant run compared with other solar plants?

Red Bud Solar Plant had a capacity factor of 4% in 2025 on 80 MW of net summer capacity, the 4th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 14 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Red Bud Solar Plant4%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is Red Bud Solar Plant generating more or less than last year?

Red Bud Solar Plant generated 27,602 MWh in 2025; EIA reports no 2024 total to compare.

Net generation by period
PeriodMWh
2024n/a
202527,602
2026 through August98,125
Monthly generation, Oct 2025 to Aug 2026
MonthMWh
August 202613,227
July 202614,808
June 202615,172
May 202616,577
April 202615,046
March 20268,915
February 20265,578
January 20268,802
December 20258,018
November 202511,492
October 20258,092

Source: EIA Form EIA-923, through August 2026.

How much of North Carolina's electricity comes from Red Bud Solar Plant?

Red Bud Solar Plant made 0.0% of the 134,194,434 MWh reported by North Carolina plants in 2025, from 0.2% of the state's 39,933 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 49th largest of 928 plants in North Carolina, the 2,965th largest of 14,327 in the U.S. and the 566th largest of 7,223 solar plants. By 2025 generation it is the 138th largest of 872 generating plants in the state.

Red Bud Solar Plant within North Carolina, 2025
MeasureThis plantNorth CarolinaShare
Capacity (MW)8039,9330.2%
Generation (MWh)27,602134,194,4340.0%
Solar capacity (MW)807,0251.1%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at Red Bud Solar Plant, and when do they retire?

1 operable generator totals 80 MW, with an average age of 0 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s180100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
68055OperatingSolar Photovoltaic802025n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns Red Bud Solar Plant?

Duke Energy Progress-(NC) is the only joint owner reported for Red Bud Solar Plant, with 100.0%. Duke Energy Carolinas, LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Duke Energy Carolinas, LLC charge homes?

Duke Energy Carolinas, LLC, the operator of Red Bud Solar Plant, had an average residential price of 13.41¢ per kWh and an average bill of $134 a month in 2025, 4% below the North Carolina average of 14.00¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst North Carolina
Duke Energy Carolinas, LLC13.41¢$1344% lower
North Carolina average14.00¢$146
U.S. average17.23¢$15123% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is Red Bud Solar Plant?

Red Bud Solar Plant is in Castalia, Nash County, North Carolina, at 36.0774° N, 78.0224° W. It sits in the Duke Energy Carolinas balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in North Carolina are similar in size?

North Carolina has 757 operable solar plants with 7,025 MW of capacity, and Red Bud Solar Plant's 80 MW is 1% of that.

Solar plants in North Carolina around this size
PlantCountyMW2025 MWh
Wilkinson Solar LLCBeaufort81161,211
Conetoe II Solar, LLCEdgecombe80152,971
Harts Mill Solar, LLCEdgecombe80173,322
Red Bud Solar PlantNash8027,602
Gutenberg SolarNorthampton80147,803
Phobos Solar, LLCNash79171,842
Trent River Solar, LLCJones79137,074

Source: EIA Forms EIA-860 and EIA-923, 2025.