Wind power plant, Texas
Sage Draw Wind power plant, Texas
Sage Draw Wind is a 338 MW wind power plant in Lynn County, Texas, operated by Sage Draw Wind, LLC, and it generated 1,151,623 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Texas, and its capacity factor sits at the 69th percentile of U.S. wind plants. By 2025 generation it ranks 677th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Sage Draw Wind plant run compared with other wind plants?
The Sage Draw Wind plant had a capacity factor of 39% in 2025 on 338 MW of net summer capacity, the 69th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 142 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Sage Draw Wind | 39% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Sage Draw Wind plant generating more or less than last year?
Generation at Sage Draw Wind fell 3.0% from 2024 to 2025, from 1,187,757 MWh to 1,151,623 MWh. Through August 2026 it is running 7.2% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 1,187,757 |
| 2025 | 1,151,623 |
| 2026 through August | 835,675 |
| 2025, same months | 779,691 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 86,263 |
| July 2026 | 70,608 |
| June 2026 | 110,923 |
| May 2026 | 106,163 |
| April 2026 | 117,048 |
| March 2026 | 129,674 |
| February 2026 | 100,677 |
| January 2026 | 114,319 |
| December 2025 | 125,676 |
| November 2025 | 100,080 |
| October 2025 | 84,624 |
| September 2025 | 61,552 |
| August 2025 | 74,480 |
| July 2025 | 71,455 |
| June 2025 | 99,806 |
| May 2025 | 95,625 |
| April 2025 | 111,262 |
| March 2025 | 137,520 |
| February 2025 | 87,202 |
| January 2025 | 102,341 |
| December 2024 | 101,838 |
| November 2024 | 103,211 |
| October 2024 | 115,924 |
| September 2024 | 64,528 |
| August 2024 | 76,324 |
| July 2024 | 75,456 |
| June 2024 | 96,539 |
| May 2024 | 115,553 |
| April 2024 | 121,669 |
| March 2024 | 108,983 |
| February 2024 | 121,052 |
| January 2024 | 86,680 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Sage Draw Wind plant, and when do they retire?
1 operable generator totals 338 MW, with an average age of 4 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 338 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| SD | Operating | Onshore Wind Turbine | 338 | 2021 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Sage Draw Wind plant?
EIA lists no joint owners for Sage Draw Wind. Sage Draw Wind, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Sage Draw Wind plant?
Sage Draw Wind is in Wilson, Lynn County, Texas, at 33.3035° N, 101.6572° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Texas are similar in size?
Texas has 228 operable wind plants with 43,942 MW of capacity, and Sage Draw Wind's 338 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Foard City Wind | Foard | 353 | 1,138,381 |
| Azure Sky Wind Project, LLC Hybrid | Throckmorton | 350 | 1,221,957 |
| BMP Wind (TX) | Callahan | 340 | 870,423 |
| Sage Draw Wind | Lynn | 338 | 1,151,623 |
| TG East | Knox | 336 | 980,794 |
| Canyon Wind Project, LLC | Scurry | 309 | 1,094,127 |
| Karankawa Wind LLC | San Patricio | 307 | 824,540 |
Source: EIA Forms EIA-860 and EIA-923, 2025.