Wind power plant, Illinois
Shady Oaks Wind Farm, Illinois
Shady Oaks Wind Farm is a 110 MW wind power plant in Lee County, Illinois, operated by Algonquin Power Co, and it generated 302,309 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Illinois, and its capacity factor sits at the 46th percentile of U.S. wind plants. By 2025 generation it ranks 1,963rd of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Shady Oaks Wind Farm plant run compared with other wind plants?
The Shady Oaks Wind Farm plant had a capacity factor of 32% in 2025 on 110 MW of net summer capacity, the 46th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 115 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Shady Oaks Wind Farm | 32% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Shady Oaks Wind Farm plant generating more or less than last year?
Generation at Shady Oaks Wind Farm fell 7.4% from 2024 to 2025, from 326,352 MWh to 302,309 MWh.
| Period | MWh |
|---|---|
| 2024 | 326,352 |
| 2025 | 302,309 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 35,790 |
| November 2025 | 19,120 |
| October 2025 | 28,266 |
| September 2025 | 11,781 |
| August 2025 | 11,449 |
| July 2025 | 11,118 |
| June 2025 | 17,082 |
| May 2025 | 26,250 |
| April 2025 | 33,361 |
| March 2025 | 43,742 |
| February 2025 | 28,083 |
| January 2025 | 36,267 |
| December 2024 | 33,752 |
| November 2024 | 34,975 |
| October 2024 | 33,103 |
| September 2024 | 14,723 |
| August 2024 | 12,953 |
| July 2024 | 9,759 |
| June 2024 | 22,874 |
| May 2024 | 20,862 |
| April 2024 | 40,780 |
| March 2024 | 41,668 |
| February 2024 | 30,603 |
| January 2024 | 30,300 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Shady Oaks Wind Farm plant, and when do they retire?
1 operable generator totals 110 MW, with an average age of 13 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 110 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Onshore Wind Turbine | 110 | 2012 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Shady Oaks Wind Farm plant?
EIA lists no joint owners for Shady Oaks Wind Farm. Algonquin Power Co operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Shady Oaks Wind Farm plant?
Shady Oaks Wind Farm is in Compton, Lee County, Illinois, at 41.6669° N, 89.0597° W. It sits in the PJM Interconnection, LLC balancing area (NERC region MRO).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Illinois are similar in size?
Illinois has 55 operable wind plants with 8,458 MW of capacity, and Shady Oaks Wind Farm's 110 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Otter Creek Wind Farm LLC | LaSalle | 150 | 450,075 |
| Ford County Wind Farm LLC | Ford | 121 | 464,720 |
| Bishop Hill III | Henry | 119 | 428,702 |
| Shady Oaks Wind Farm | Lee | 110 | 302,309 |
| Shady Oaks Wind 2 | Lee | 108 | 318,179 |
| Blackstone Wind Farm LLC | Livingston | 106 | 237,659 |
| Midland Wind | Henry | 106 | 346,152 |
Source: EIA Forms EIA-860 and EIA-923, 2025.