Wind power plant, Texas
Silver Star I Wind Power Project, Texas
Silver Star I Wind Power Project is a 52.8 MW wind power plant in Erath County, Texas, operated by Silver Star I Power Partners LLC, and it generated 204,866 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 89th percentile of U.S. wind plants. By 2025 generation it ranks 2,459th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Silver Star I Wind Power Project plant run compared with other wind plants?
The Silver Star I Wind Power Project plant had a capacity factor of 44% in 2025 on 52.8 MW of net summer capacity, the 89th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 162 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Silver Star I Wind Power Project | 44% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Silver Star I Wind Power Project plant generating more or less than last year?
Generation at Silver Star I Wind Power Project rose 2.2% from 2024 to 2025, from 200,544 MWh to 204,866 MWh.
| Period | MWh |
|---|---|
| 2024 | 200,544 |
| 2025 | 204,866 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 20,675 |
| November 2025 | 18,853 |
| October 2025 | 17,577 |
| September 2025 | 11,716 |
| August 2025 | 11,083 |
| July 2025 | 15,872 |
| June 2025 | 18,423 |
| May 2025 | 15,072 |
| April 2025 | 22,610 |
| March 2025 | 22,722 |
| February 2025 | 15,455 |
| January 2025 | 14,808 |
| December 2024 | 16,578 |
| November 2024 | 19,743 |
| October 2024 | 18,743 |
| September 2024 | 9,085 |
| August 2024 | 14,220 |
| July 2024 | 13,989 |
| June 2024 | 16,596 |
| May 2024 | 15,444 |
| April 2024 | 21,700 |
| March 2024 | 19,986 |
| February 2024 | 19,986 |
| January 2024 | 14,474 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Silver Star I Wind Power Project plant, and when do they retire?
1 operable generator totals 52.8 MW, with an average age of 17 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2000s | 1 | 53 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Onshore Wind Turbine | 53 | 2008 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Silver Star I Wind Power Project plant?
2 owners report shares in Silver Star I Wind Power Project; Texas Wind Repower HoldCo, L.P. c/o Concord Infrastructure Investments, LLC holds the largest named share, 66.6% or about 35.2 MW. Silver Star I Power Partners LLC operates the plant.
| Owner | Share | MW | 2025 MWh, by share |
|---|---|---|---|
| Texas Wind Repower HoldCo, L.P. c/o Concord Infrastructure Investments, LLC | 66.6% | 35 | 136,441 |
| UBS Asset Management (Americas) Inc | 33.4% | 18 | 68,425 |
Source: EIA Form EIA-860, Owner, 2025 final. MW and MWh by share multiply the plant totals by each owner's percentage.
Where is the Silver Star I Wind Power Project plant?
Silver Star I Wind Power Project is in Dublin, Erath County, Texas, at 32.3387° N, 98.4761° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Texas are similar in size?
Texas has 228 operable wind plants with 43,942 MW of capacity, and Silver Star I Wind Power Project's 52.8 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Cirrus Wind 1 LLC | Lynn | 61 | n/a |
| Whirlwind Energy Center | Floyd | 60 | 89,669 |
| Ocotillo Windpower | Howard | 59 | 79,406 |
| Silver Star I Wind Power Project | Erath | 53 | 204,866 |
| Cotton Plains Wind Farm | Floyd | 50 | 181,894 |
| Hidalgo Wind Farm II | Hidalgo | 50 | 152,788 |
| Sunray Wind I | Moore | 50 | 131,397 |