Wind power plant, Texas
Whirlwind Energy Center, Texas
Whirlwind Energy Center is a 59.8 MW wind power plant in Floyd County, Texas, operated by Whirlwind Energy LLC, and it generated 89,669 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 7th percentile of U.S. wind plants. By 2025 generation it ranks 3,515th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Whirlwind Energy Center plant run compared with other wind plants?
The Whirlwind Energy Center plant had a capacity factor of 18% in 2025 on 57 MW of net summer capacity, the 7th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 66 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Whirlwind Energy Center | 18% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Whirlwind Energy Center plant generating more or less than last year?
Generation at Whirlwind Energy Center fell 11.6% from 2024 to 2025, from 101,474 MWh to 89,669 MWh.
| Period | MWh |
|---|---|
| 2024 | 101,474 |
| 2025 | 89,669 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 10,120 |
| November 2025 | 6,051 |
| October 2025 | 7,603 |
| September 2025 | 6,198 |
| August 2025 | 6,406 |
| July 2025 | 5,877 |
| June 2025 | 7,456 |
| May 2025 | 7,649 |
| April 2025 | 8,819 |
| March 2025 | 7,777 |
| February 2025 | 6,853 |
| January 2025 | 8,860 |
| December 2024 | 6,593 |
| November 2024 | 825 |
| October 2024 | 11,267 |
| September 2024 | 6,445 |
| August 2024 | 8,096 |
| July 2024 | 7,829 |
| June 2024 | 8,388 |
| May 2024 | 9,051 |
| April 2024 | 9,569 |
| March 2024 | 10,402 |
| February 2024 | 13,228 |
| January 2024 | 9,781 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Whirlwind Energy Center plant, and when do they retire?
1 operable generator totals 59.8 MW, with an average age of 18 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2000s | 1 | 60 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| WEC | Operating | Onshore Wind Turbine | 60 | 2007 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Whirlwind Energy Center plant?
EIA lists no joint owners for Whirlwind Energy Center. Whirlwind Energy LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Whirlwind Energy Center plant?
Whirlwind Energy Center is in Floydada, Floyd County, Texas, at 34.1050° N, 101.0986° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Texas are similar in size?
Texas has 228 operable wind plants with 43,942 MW of capacity, and Whirlwind Energy Center's 59.8 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Sendero | Jim Hogg | 78 | 274,340 |
| Windthorst-2 | Archer | 68 | 181,550 |
| Cirrus Wind 1 LLC | Lynn | 61 | n/a |
| Whirlwind Energy Center | Floyd | 60 | 89,669 |
| Ocotillo Windpower | Howard | 59 | 79,406 |
| Silver Star I Wind Power Project | Erath | 53 | 204,866 |
| Cotton Plains Wind Farm | Floyd | 50 | 181,894 |
Source: EIA Forms EIA-860 and EIA-923, 2025.