Skip to main content
RateWatt

Biomass power plant, California

SPI Anderson 2 biomass power plant, California

SPI Anderson 2 is a 30.2 MW biomass power plant in Shasta County, California, operated by Sierra Pacific Industries, and it generated 122,087 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in California, and its capacity factor sits at the 55th percentile of U.S. biomass plants. By 2025 generation it ranks 3,178th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

30.2 MWNameplate capacity
51%Capacity factor, 2025, 55th percentile, on 27.2 MW net summer
0.1%Of CA generation, 2025
10 yearsAverage generator age, by MW

How hard does the SPI Anderson 2 plant run compared with other biomass plants?

The SPI Anderson 2 plant had a capacity factor of 51% in 2025 on 27.2 MW of net summer capacity, the 55th percentile of the 167 U.S. biomass plants with at least 20 MW. The typical biomass plant reached 48%. That equals about 186 days at full output out of 365.

0%Shaded: the middle half of biomass plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
SPI Anderson 251%
Biomass plants, 75th percentile65%
Biomass plants, median48%
Biomass plants, 25th percentile35%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the SPI Anderson 2 plant generating more or less than last year?

SPI Anderson 2 generated 122,087 MWh in 2025; EIA reports no 2024 total to compare. 2024 has output for only 10 months, so the two years are not compared.

Net generation by period
PeriodMWh
2024117,805
2025122,087
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 202510,856
November 202512,716
October 202514,050
September 202512,851
August 202514,698
July 202512,905
June 202514,013
May 202514,802
April 202513,763
March 20251,433
February 20250
January 20250
December 20240
November 20240
October 20248,031
September 202413,194
August 202413,878
July 202413,701
June 202412,895
May 202411,721
April 20246,977
March 202412,718
February 202411,918
January 202412,772

Source: EIA Form EIA-923, through August 2026.

How much of California's electricity comes from the SPI Anderson 2 plant?

SPI Anderson 2 made 0.1% of the 204,542,898 MWh reported by California plants in 2025, from 0.0% of the state's 107,433 MW of capacity. Its share of output is 2.1 times its share of capacity. By capacity it is the 551st largest of 1,877 plants in California, the 4,348th largest of 14,327 in the U.S. and the 140th largest of 585 biomass plants. By 2025 generation it is the 329th largest of 1,608 generating plants in the state.

SPI Anderson 2 within California, 2025
MeasureThis plantCaliforniaShare
Capacity (MW)30107,4330.0%
Generation (MWh)122,087204,542,8980.1%
Biomass capacity (MW)301,0892.8%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the SPI Anderson 2 plant, and when do they retire?

1 operable generator totals 30.2 MW, with an average age of 10 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s130100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
GEN1OperatingWood/Wood Waste Biomass302015n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the SPI Anderson 2 plant?

EIA lists no joint owners for SPI Anderson 2. Sierra Pacific Industries operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the SPI Anderson 2 plant?

SPI Anderson 2 is in Anderson, Shasta County, California, at 40.4723° N, 122.3242° W. It sits in the California Independent System Operator balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which biomass plants in California are similar in size?

California has 99 operable biomass plants with 1,089 MW of capacity, and SPI Anderson 2's 30.2 MW is 3% of that.

Biomass plants in California around this size
PlantCountyMW2025 MWh
Hyperion Treatment Plant CHP PlantLos Angeles33103,806
Humboldt Sawmill CompanyHumboldt33106,452
Burney Forest ProductsShasta3171,993
SPI Anderson 2Shasta30121,201
Wadham EnergyColusa29144,032
Woodland Biomass Power LtdYolo28161,131
Covanta MendotaFresno28n/a