Skip to main content
RateWatt

Solar power plant, Tennessee

SR Bell Buckle solar power plant, Tennessee

SR Bell Buckle is a 35 MW solar power plant in Bedford County, Tennessee, operated by SR Bell Buckle, LLC, and it generated 68,997 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Tennessee, and its capacity factor sits at the 45th percentile of U.S. solar plants. By 2025 generation it ranks 3,768th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

35 MWNameplate capacity
23%Capacity factor, 2025, 45th percentile, on 35 MW net summer
0.1%Of TN generation, 2025
2 yearsAverage generator age, by MW

How hard does the SR Bell Buckle plant run compared with other solar plants?

The SR Bell Buckle plant had a capacity factor of 23% in 2025 on 35 MW of net summer capacity, the 45th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 82 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
SR Bell Buckle23%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the SR Bell Buckle plant generating more or less than last year?

Generation at SR Bell Buckle fell 0.7% from 2024 to 2025, from 69,450 MWh to 68,997 MWh. Through August 2026 it is running 5.1% ahead of the same months of 2025.

Net generation by period
PeriodMWh
202469,450
202568,997
2026 through August52,725
2025, same months50,175
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 20268,020
July 20267,459
June 20267,833
May 20267,672
April 20268,156
March 20266,047
February 20264,157
January 20263,381
December 20252,781
November 20253,943
October 20255,380
September 20256,718
August 20256,903
July 20258,631
June 20257,601
May 20256,410
April 20256,872
March 20256,604
February 20253,584
January 20253,570
December 20242,888
November 20243,472
October 20246,607
September 20245,697
August 20248,370
July 20246,343
June 20248,416
May 20247,552
April 20246,749
March 20246,236
February 20244,473
January 20242,647

Source: EIA Form EIA-923, through August 2026.

How much of Tennessee's electricity comes from the SR Bell Buckle plant?

SR Bell Buckle made 0.1% of the 74,359,316 MWh reported by Tennessee plants in 2025, from 0.1% of the state's 23,342 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 44th largest of 99 plants in Tennessee, the 4,234th largest of 14,327 in the U.S. and the 993rd largest of 7,223 solar plants. By 2025 generation it is the 46th largest of 95 generating plants in the state.

SR Bell Buckle within Tennessee, 2025
MeasureThis plantTennesseeShare
Capacity (MW)3523,3420.1%
Generation (MWh)68,99774,359,3160.1%
Solar capacity (MW)358194.3%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the SR Bell Buckle plant, and when do they retire?

1 operable generator totals 35 MW, with an average age of 2 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s135100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
SRBELOperatingSolar Photovoltaic352023n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the SR Bell Buckle plant?

EIA lists no joint owners for SR Bell Buckle. SR Bell Buckle, LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the SR Bell Buckle plant?

SR Bell Buckle is in Shelbyville, Bedford County, Tennessee, at 35.5700° N, 86.4600° W. It sits in the Tennessee Valley Authority balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Tennessee are similar in size?

Tennessee has 45 operable solar plants with 819 MW of capacity, and SR Bell Buckle's 35 MW is 4% of that.

Solar plants in Tennessee around this size
PlantCountyMW2025 MWh
SR McKellarMadison70139,019
Millington Solar FarmShelby5393,143
SR Bell BuckleBedford3568,997